Q18 Single choice

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget.
Management wants to know what the project's cost performance index (CPI) is.

What value do you report?