Q19 Single choice

During an audit of a contract for computer security, a governmental auditor finds that a contractor has developed a system that could be the most advanced in the industry.
If it seems that the contractor is charging the government for developmental cost of a system that might be sold to other organizations, what is the auditor's best course of action?