A PMO professional joins an existing PMO that displays warning signs that the organization's perception of the PMO's value is deteriorating.
Which step should the PMO professional recommend?
Show answer and explanation
Correct answer: B
To reverse a deteriorating value perception, the PMO professional shouldeffectively communicate the PMO' s benefits using both qualitative stories and quantitative metrics . Demonstrating value in measurable and relatable terms reinforces stakeholder confidence.
Reducing costs (Option A) or changing personnel (Option C) are less direct and may not impact perception quickly. Changing reporting lines (Option D) is a structural change that may not address value communication.
PMI-PMOCP Strategic Alignment emphasizes benefits communication as a core step in value restoration.
References:
PMI-PMOCP Exam Content Outline, Strategic Alignment Domain
PMI Practice Standard for Project Management Offices (2013), Value Communication
PMI PMO Value Ring, Stakeholder Engagement