Which role facilitates assessments of the impact of changes on the target operating model?
A. Senior responsible owner
B. Programme manager
C. Business change manager
D. Programme office
Why should stakeholders’ influence and interests be compared?
A. To define the areas of the programme that affect each stakeholder
B. To identify the various stakeholders from their interests
C. To ensure communication channels are exploited effectively
D. To understand how the programme will affect their working environment
Which describes an impact of a risk?
A. Effect on the programme if something goes wrong
B. An event that might increase a programme's outcome
C. The amount of risk that will be tolerated
D. Possibility that something will go wrong
What type of programme may also be referred to as a ‘must do’ programme?
A. Portfolio
B. Emergent
C. Vision-led
D. Compliance
Which occurs in identifying a Programme?
A. Consolidation of the outputs from identifying a Programme in the Programme Definition Document
B. Confirmation of the Programme Mandate to trigger the start of the programme
C. Appointment of the Business Change Team to prepare the Programme Mandate
D. Creation of the Stakeholder Engagement Strategy to support consultation on the Programme Brief
Which response pays a third party to accept a risk?
A. Transfer
B. Prepare contingent plans
C. Accept
D. Avoid
What document describes a programme's projects, their timescales and dependencies?
A. Project brief
B. Highlight report
C. Blueprint
D. Projects Dossier
Which is NOT a characteristic of the programme management principles?
A. They enable practitioners to achieve transformational change
B. They have been successful when applied in practice
C. They ensure practitioners follow common procedures
D. They are valid in all programme management contexts
Which governance theme includes carrying out an assessment of the effectiveness of the decisions taken by programme leaders?
A. Blueprint Design and Delivery
B. Leadership and Stakeholder Engagement
C. Quality and Assurance Management
D. Programme Organization
Which role is MOST likely to have a focus on managing the costs of training operational teams during transition?
A. Business Change Manager
B. Programme Manager
C. Senior Responsible Owner
D. Programme Office
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only MSP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your MSP-FOUNDATION exam preparations and MSP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.