Which is a programme management principle?
A. Adding value
B. Vision
C. Identifying a programme
D. Corporate strategy
Which information about a project should be included in the Projects Dossier?
A. How the outputs will be implemented into the business
B. Contribution the project will make to the programme's benefits
C. Names of the project team members
D. Project brief for the project
Which is a response option to an identified threat?
A. Identify the tranche in which it might materialize
B. Assign responsibility for it to the Programme Manager
C. Accept the risk
D. Adjust the risk appetite
Which of the following statements about successful stakeholder engagement are true?
1.
It is more active and embracing than communication.
2.
It includes stakeholders in decision making and implementation.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 is true
Which role focuses on monitoring the progress of the programme at a strategic level?
A. Sponsoring group
B. Programme manager
C. Senior responsible owner
D. Risk manager
Which is NOT a reason for Managing the Tranches?
A. To implement the Risk Management Strategy
B. To coordinate and manage project delivery
C. To maintain focus on stable operations
D. To maintain information and asset integrity
Which document is updated throughout the programme when new information on benefits and risks becomes available?
A. Benefits Management Strategy
B. Business Case
C. Programme Brief
D. Information Management Plan
Which of the following statements about the core elements of successful communications is true?
1.
Stakeholder analysis is required
2.
Audit trail is established
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 is true
What is the BEST reason for using programme management?
A. It removes the need for strong leadership
B. It concentrates on delivering outputs
C. It provides a vision for the entire organization
D. It enables stakeholder engagement
Which of the following statements about programme dependencies is true?
1.
Internal dependencies include dependencies on strategic decisions
2.
Internal dependencies are likely to be linked to the scope of a corporate portfolio
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 is true
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only MSP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your MSP-FOUNDATION exam preparations and MSP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.