IFMA IFMA-CFM Online Questions & Answers

  • Question 151:

    As the Facility Manager, you secured 5,500 square feet of Class A office space on a multi-tenant floor to support a two-year business initiative. To minimize capital investment, the space will be used with pre-existing furnishings, fixtures, and equipment. However, before you can move people into this space, you will need a certificate of occupancy. What system must be examined to obtain a certificate of occupancy?

    A. Life safety system
    B. Potable water system
    C. Network connections
    D. Telephone system

  • Question 152:

    What action should be completed first when developing a real estate master plan?

    A. Perform an environmental review
    B. Review the strategic plan
    C. Meet with key stakeholders
    D. Perform highest and best use studies

  • Question 153:

    What is the BEST approach to using organizational communication to foster employee support for sustainability efforts?

    A. Over-communicate by including every aspect of the organization’s sustainability efforts.
    B. Challenge employees with goals that might be unrealistic but help to create a vision for the future.
    C. Create enthusiasm through articulate and succinct communication.
    D. Compare the organization's sustainability efforts to other companies to create a sense of competition.

  • Question 154:

    What level of damage and risk is anticipated with the current building code requirements for most buildings?

    A. Buildings will have minor damage and occupants can continue to occupy the building after an event.
    B. Buildings will have very little or no damage with no impact on the occupancy and operations.
    C. Buildings will have damage but will not collapse and allow time for occupants to leave the building.

  • Question 155:

    There has been a recent increase in complaints of items stolen from people's desks within a facility. What is the facility manager's initial step regarding the security of the staff and facility?

    A. Install security cameras throughout the facility to ensure you capture future incidents.
    B. Update your security procedures to ensure that staff maintain a secure desk.
    C. Investigate each case and remind staff to ensure all valuables are locked.
    D. Turn the matter over to a professional security company to lead an investigation.

  • Question 156:

    During regular preventive maintenance activities, you notice green algae and scaling on the interior walls of the cooling tower. What action should you take to resolve the concerns?

    A. Shutdown the tower, allow surfaces to dry, and scrape biological growth from interior walls before returning the tower to operation.
    B. Test the cooling tower water, adjust the frequency of chemical balancing, and flush if needed.
    C. Perform a building occupant health survey to determine any adverse effects, and then adjust the injection levels of balancing chemicals.
    D. Drain the tower and then complete a fresh-water flush using warm water, and add new balancing chemicals.

  • Question 157:

    The building automation systems (BAS) experienced a power loss. The systems are now back online and are accessible by remote monitoring controls. From a remote login, you observe that the indoor air temperatures are warmer than the settings. What should you do?

    A. Lower the temperature set points to cool down the building faster.
    B. Call an onsite occupant to verify the office space temperatures.
    C. Dispatch staff to physically check all equipment for proper operations.
    D. Recommend to the owner to install a generator to minimize the impact of future outages.

  • Question 158:

    What is an Integrated Workplace Management System (IWMS)?

    A. An energy-efficient tool to operate HVAC systems.
    B. Requires a BAS system to be in place.
    C. An enterprise-level software platform that facilitates integration of data.
    D. Must be replaced or updated every 5 years to remain viable.

  • Question 159:

    What best describes a Building Automation System (BAS)?

    A. A system supporting two-way communication between controllers and devices, automated decisions, and analysis.
    B. A one-way control mechanism for multiple core building systems.
    C. A system that integrates various facility management functions, including building security and facility space metrics.
    D. A system that does not operate third-party systems.

  • Question 160:

    Recently, an organization has flattened its structure versus that of a typical pyramid structure. As part of the restructure, the existing office building will be renovated. What type of design elements should a facility manager consider in the renovation?

    A. Offices for management, teaming areas, shorter workstation panels, and large conference rooms
    B. Team areas, bigger workstations for files, offices for senior management, and fewer meeting rooms
    C. Space for employee interaction, team areas, smaller workstations, and shorter panels

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IFMA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your IFMA-CFM exam preparations and IFMA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.