IASSC Lean Six Sigma Black Belt ICBB IASSC-ICBB Questions & Answers

  • Question 31:

    A Belt rearranged the location of the parts inventory for a rework station locating the most often used parts to be within hand reach of the repair person. This rearrangement resulted in quicker repair times by eliminating one of seven major elements of waste which is the Waste of __________.

    A. Motion

    B. Conveyance

    C. Inventory

    D. Waiting

  • Question 32:

    The primary objective in removal of waste is to improve the Order Production Cycle where the time from _________________ to the time of receipt of payment is compressed.

    A. Shift start

    B. Product development

    C. Receipt of an order

    D. New fiscal year

  • Question 33:

    What dollar amount of savings would a project show if it reduced your outstanding Accounts Receivable by $0.9 million dollars to $3.5 million total and your organization's marginal cost of capital was 5.7%?

    A. $49,250

    B. $51,300

    C. $117,500

    D. $202,424

  • Question 34:

    Handling of warranty returns, process improvement team meetings and rework to meet customer expectations are all examples of business costs that are classified as ___________ .

    A. Nuisance

    B. Non-value Add

    C. Necessary

    D. Unavoidable

  • Question 35:

    The Japanese born function of a Kaizen event utilizes a specific, step-by-step approach meant to bring about major changes to a process.

    A. True

    B. False

  • Question 36:

    Which of these are examples of business metrics or Key Performance Indicators commonly referred to as KPI's?

    A. Cycle Time

    B. Defects

    C. No. of Units Reworked

    D. Labor Hours

    E. All of these answers are correct

  • Question 37:

    As a means of measuring the effects on other areas of a process as a result of changes in the primary metric we also define and track ________________.

    A. Parallel process metrics

    B. Secondary metrics

    C. Tertiary metrics

    D. Industry standards

  • Question 38:

    "A calculated time frame that matches customer demand" is a definition of what Lean Principles term?

    A. Value Stream

    B. Kaizen event

    C. Takt time

    D. Kanban

  • Question 39:

    When one speaks of 20% of something contributing 80% of the affect they are referring to what is known as the _________________.

    A. Shewhart Example

    B. Connection Principle

    C. Balance Equation

    D. Pareto Principle

  • Question 40:

    Using this data calculate the percentage of DPU. Data: 763 defects, 18,000 units.

    A. 2.12

    B. 3.42

    C. 4.24

    D. 5.72

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IASSC exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your IASSC-ICBB exam preparations and IASSC certification application, do not hesitate to visit our Vcedump.com to find your solutions here.