The more PUE value of a data center is close to 1, the better energy usage efficiency is.
A. TRUE
B. FALSE
When the temperature detector or smoke detector in the FusionModule1000 generates an alarm, ( ) emits a continuous beeping sound to remind you to take measures as soon as possible to avoid a major accident. (Choose all apply)
A. Electricity or voltage ratio setting error
B. The corresponding voltage collection line is abnormal.
C. Corresponding current transformer failure
D. Intelligent power meter failure
In the battery model 6-GFM-150, 150 indicates () of battery?
A. Actual Capacity
B. Rated Capacity
C. Maximum Capacity
D. Load Capacity
To set the remote alarm notification on the NetEco, you need to ( ). (Choose all apply)
A. Set notification templates
B. Set notification templates
C. Set the user
D. Set remote notification rules
( ) can connect to the AI/DI port on the access actuator.
A. IC card reader
B. Fingerprint and card reader
C. Exit button
D. Magnetic
Users can modify IP Address of the ( ) menu.
A. Active alarm
B. Alarm notification
C. Time settings
D. Monitor module IP
First time powering on UPS5000-E, make sure that the UPS main input switch, bypass switch, output switch, maintenance bypass switch and battery switch are all OFF
A. TRUE
B. FALSE
The Ibat2.0, optional component of the UPS5000-E, can detect () of each battery. (Choose 3)
A. Frequency
B. Voltage
C. Internal resistance
D. Battery poles temperature
The alarm management functions of the ECC800 include ( ). (Choose all apply)
A. Viewing historical alarms
B. Filtering alarms
C. Exporting alarms
D. Setting alarm parameters
Which procedure is correct about powering on UPS5000?
A. 1. Turn on the main and bypass input switches 2.Start the inverter 3.Set parameters and check system status. 4.Turn on the battery switch. 5.Start loads
B. 1. Set parameters and check system status. 2.Turn on the main and bypass input switches 3.Start the inverter 4.Turn on the battery switch. 5.Start loads
C. 1. Turn on the main and bypass input switches 2.Set parameters and check system status. 3.Turn on the battery switch. 4.Start the inverter 5.Start loads
D. 1. Turn on the main and bypass input switches 2.Set parameters and check system status. 3.Start the inverter 4.Turn on the battery switch. 5.Start loads
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Huawei exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your H12-425 exam preparations and Huawei certification application, do not hesitate to visit our Vcedump.com to find your solutions here.