  • Question 31:

    Which of the following statements about the Project Initiation Documentation are true?

    1.

    The Project Initiation Documentation is used to ensure that a sound basis exists.

    2.

    The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project.

    A. Only 1 is true
    B. Only 2 is true
    C. Both 1 and 2 are true
    D. Neither 1 or 2 are true

  • Question 32:

    Which is a purpose of quality planning?

    A. Define the structure of the project management team
    B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
    C. Document approval records for those project products that have met their quality criteria
    D. Produce the Project Plan with resource and schedule information

  • Question 33:

    Which is a responsibility of the managing level within the project management team?

    A. Set project tolerances
    B. Approve stage completion
    C. Ensure that the products are produced within the constraints agreed with the Project Board
    D. Appoint the project management team

  • Question 34:

    Which of the following is NOT an event-driven control?

    A. Project mandate
    B. Checkpoint Report
    C. Exception Report
    D. End of a stage

  • Question 35:

    Which is part of the PRINCE2 definition of a project?

    A. An undertaking that consists of at least two management stages
    B. A description of what must be delivered in order to gain acceptance
    C. The total of a plan's products
    D. A temporary organization that is created for the purpose of delivering business products

  • Question 36:

    How many tasks does the product-based planning technique describe?

    A. One
    B. Two
    C. Three
    D. Four

  • Question 37:

    If an informal issue is defined as a problem or concern, where should it first be recorded?

    A. Issue Register
    B. Risk Register
    C. Daily Log
    D. Exception Report

  • Question 38:

    If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

    A. Senior User
    B. Executive
    C. Corporate/programme management
    D. Senior Supplier

  • Question 39:

    Which statement describes the responsibilities of a risk actionee?

    A. Identifying risks to the project that might occur in their department
    B. Owning and authorizing the use of the risk budget to fund risk responses
    C. Managing, monitoring and controlling of all aspects of an assigned risk
    D. Carrying out a risk response action to respond to a particular risk

  • Question 40:

    What theme provides all management levels within the project management team with mechanisms for monitoring and control?

    A. Progress
    B. Change
    C. Organization
    D. Quality

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your EX0-002 exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.