  • Question 261:

    This will be a:

    A. left-tail test
    B. right-tail test
    C. two-tail test

  • Question 262:

    One of the foundations of Lean Six Sigma is the concept that the output of a process (Y) is influenced by the process inputs (X's) and is commonly shown as which formula?

    A. Y = Z(X2)
    B. Y = f(X3)
    C. Y = f(Xn)
    D. Y = g(X+ 1.5)

  • Question 263:

    The Organization Specification limits are + 5 or - 5 % whereas Control Limits are + 6 % and - 2%, justify whether the Process is?

    A. Stable
    B. Capable
    C. Within control
    D. None of the above

  • Question 264:

    Which of the following techniques can be used in regression analysis to reduce higher- order terms in the model?

    A. Large samples
    B. Dummy variables
    C. Transformations
    D. Blocking

  • Question 265:

    From this list select the best example of Bias in Sampling.

    A. Testing the completeness of cooking a cake but the testers cannot agree on how to measure internal temperature
    B. Testing the sharpness of a razor blade while the sample of 500 are from the same model razor
    C. Testing the weight of participants at a wrestling event and only measuring those who finished second or better
    D. Testing a hand-held GPS models for durability using samples only from Nokia Model P120

  • Question 266:

    From the variance F-test shown above, which of these conclusions is/are valid?

    A. The variance between the class score distribution is significantly different
    B. The variance between the class score distribution is not significantly different
    C. This test applies only to Normal Distributed data at 99 % confidence
    D. This test applies only to Non-normal Data at 99 % confidence
    E. There are not enough data points to make any statistical conclusions

  • Question 267:

    Perform a risk analysis to determine the expected profit or (loss) from a project which has four possible disjoint outcomes: Outcome A shows a profit of $340,000 and has a probability of 0.25 Outcome B shows a profit of $120,000 and has a probability of 0.40 Outcome C shows a loss of $40,000 and has a probability of 0.10 Outcome D shows a profit of $100,000 and has a probability of 0.25

    A. $130,000
    B. $520,000
    C. $154,000
    D. ($168,000)
    E. none of the above

  • Question 268:

    If a process follows an exponential distribution with a mean of 25, what is the standard deviation for the process?

    A. 0.4
    B. 5.0
    C. 12.5
    D. 25.0

  • Question 269:

    Poka-yoke is best defined as

    A. improving machine efficiency
    B. reducing field failures to virtually zero
    C. capturing the voice of the customer
    D. preventing controllable defects

  • Question 270:

    A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiring that the average cost of an internal critical raw material component be less than or equal to $4,200 in order to stay within budget. Using a sample of 35 first article components, a Mean of the new product upgrade price of $4,060, and a Standard Deviation of $98 was estimated. Select the answer that best states the Practical Problem.

    A. If the average cost per component is $4,200 or less, then the purchase manager will introduce the new product upgrade with new components.
    B. If the average cost per component is greater than $4,200, then the purchase manager will introduce the new product upgrade with new components.
    C. Only if the average cost per product upgrade is $4,060, will the purchase manager introduce new product upgrades with new components.
    D. If the average cost per new product upgrade is less than $180, then the purchase manager will introduce the new product upgrade with new components.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Six Sigma exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CLSSBB exam preparations and Six Sigma certification application, do not hesitate to visit our Vcedump.com to find your solutions here.