  • Question 71:

    The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions)

    A. 4.62

    B. 4.24

    C. 4.10

    D. 4.31

  • Question 72:

    The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. What is the cost of manufacturing labor for the piece of equipment today?

    A. $140,000

    B. $875,000

    C. $210,000

    D. $105,000

  • Question 73:

    The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. 10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours were planned?

    A. 10,586

    B. 9,280

    C. 9,559

    D. 10,278

  • Question 74:

    The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. 9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. Based on current trends, how many hours will be expended at project completion?

    A. 16,215

    B. 14,201

    C. 12,000

    D. 10,526

  • Question 75:

    The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. 10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours have been earned?

    A. 9,979

    B. 10,586

    C. 11,052

    D. 9,559

  • Question 76:

    The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. 9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current schedule performance index (SPI)?

    A. 0.96

    B. 0.88

    C. 0.84

    D. 1.14

  • Question 77:

    The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. 9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current cost performance index (CPI)?

    A. 0.96

    B. 0.84

    C. 1.14

    D. 0.88

  • Question 78:

    The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. 6,573 hours have been expended to date. Planned completion at this time is 60%. The project is determined to be 55% complete. How many hours have been earned?

    A. 6,600

    B. 6,960

    C. 7,200

    D. 6,573

  • Question 79:

    In a fixed price contract the:

    A. Contractor has no risk in the project

    B. Contactor assumes all the performance risk

    C. Contractor is paid for actual costs

    D. Owner has all the risk

  • Question 80:

    The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project?

    A. 45%

    B. 50%

    C. 95%

    D. 30%

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only AACE International exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CCP exam preparations and AACE International certification application, do not hesitate to visit our Vcedump.com to find your solutions here.