Skip to main content

CCE-CCC Real Exam Questions

Certified Cost Consultant / Cost Engineer (AACE International)

115 questions available · Page 1 of 12

Updated Exam DumpsVerified AnswersPass Guarantee

Get Complete Exam Dumps
Question 1 Single choice

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be
$22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

If $100,000 is needed to purchase a piece of equipment 3 years from now, how much money needs to be invested today assuming a 10% rate of return (rounded to the nearest thousand)?

  1. A

    $78,000

  2. B

    $70,000

  3. C

    $75,000

  4. D

    $82,000

Show answer and explanation

Correct answer: C

Question 2 Single choice

Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is:

  1. A

    Activity ID

  2. B

    WBS Code

  3. C

    Resource

  4. D

    Account number

Show answer and explanation

Correct answer: A

Question 3 Single choice

The four steps to writing are:

  1. A

    Introduction, paragraph, conclusion, works cited

  2. B

    Start, write, complete, revise

  3. C

    Abstract, body conclusion, bibliography

  4. D

    Plan, write, cool, revise

Show answer and explanation

Correct answer: D

Question 4 Single choice

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

A cyclical process model was chosen as the basis for total cost management (TCM) because:

  1. A

    It is one of the basic tenets of quality improvement

  2. B

    Refinement is needed to prepare the estimate at completion (EAC)

  3. C

    Strategic assets and projects have inherent life cycles

  4. D

    It facilitates development of budgets and schedules

Show answer and explanation

Correct answer: C

Question 5 Single choice

What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?

  1. A

    Liability insurance

  2. B

    Performance bond

  3. C

    Bid bond

  4. D

    Surety bond

Show answer and explanation

Correct answer: B

Question 6 Single choice

The goal of listening is to:

  1. A

    Analyze what the speaker is saying

  2. B

    Find out what is going on

  3. C

    Have time to formulate your thoughts on the subject

  4. D

    Improve communication

Show answer and explanation

Correct answer: D

Question 7 Single choice

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed.

What percent complete is this project?

  1. A

    45%

  2. B

    50%

  3. C

    95%

  4. D

    30%

Show answer and explanation

Correct answer: A

Question 8 Single choice

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

  1. A

    Activity total slack

  2. B

    Remaining duration

  3. C

    Just-in-time" scheduling

  4. D

    Free float

Show answer and explanation

Correct answer: A

Question 9 Single choice

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve.
Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the company needs to repay a loan of $100,000 in 10 uniform annual payments, how much will each payment be?

  1. A

    $16,380

  2. B

    $16,578

  3. C

    $15,937

  4. D

    $16,273

Show answer and explanation

Correct answer: D

Question 10 Single choice

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

An unbalanced bid methodology can best be used by:

  1. A

    Engineer/contractor working for the owner (Plan B)

  2. B

    Subcontractor working for contractor (Plan A or B)

  3. C

    Contractor working directly for engineer (plan A or B)

  4. D

    Engineer working for the owner (Plan A)

Show answer and explanation

Correct answer: A