CAPM Exam Details

  • Exam Code
    :CAPM
  • Exam Name
    :Certified Associate in Project Management (CAPM)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :1470 Q&As
  • Last Updated
    :May 28, 2026

PMI CAPM Online Questions & Answers

  • Question 981:

    Expected monetary value (EMV) is computed by which equation?

    A. Value of each possible outcome multiplied by probability of occurrence
    B. Value of each possible outcome multiplied by probability of non-occurrence
    C. Multiplying the value of each possible outcome by the probability of occurrence and adding the products together
    D. Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

  • Question 982:

    The following is a network diagram for a project.

    What is the critical path for the project?

    A. A-B-D-G
    B. A-B-E-G
    C. A-C-F-G
    D. A-C-E-G

  • Question 983:

    Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

    A. Cost management plan
    B. Quality management plan
    C. Communications management plan
    D. Risk management plan

  • Question 984:

    An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project.

    What data should be included in this information radiator?

    A. Key performance indicators (KPIs) and baseline
    B. Product and sprint backlog
    C. Burndown and burnup charts
    D. Increments and bottlenecks

  • Question 985:

    The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

    A. Earned value management.
    B. Forecasting.
    C. Critical chain methodology.
    D. Critical path methodology.

  • Question 986:

    Which of the following are documented directions to perform an activity that can reduce the probability of negative consequences associated with project risks?

    A. Recommended corrective actions
    B. Recommended preventive actions
    C. Risk audits
    D. Risk reassessments

  • Question 987:

    Which tool is used to develop technical details within the project management plan?

    A. Expert judgment
    B. Project management methodology
    C. Project management information system (PMIS)
    D. Project selection methods

  • Question 988:

    When can pre-assignment of project team members occur?

    A. When the project uses capital expenditures
    B. When the required staff can be acquired from outside sources
    C. When the project would be ignored due to travel expenses
    D. When the project is the result of specific people being promised as part of a competitive proposal

  • Question 989:

    Which procurement management process includes obtaining seller response, seller selection, and contract awarding?

    A. Plan Procurement
    B. Manage Procurement
    C. Conduct Procurements
    D. Perform Procurement

  • Question 990:

    Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

    A. Direct
    B. Interactive
    C. Pull
    D. Push

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.