  • Question 921:

    Which of the following is a category of organizational process assets?

    A. Government standards
    B. Organizational culture
    C. Employee capabilities
    D. Organizational knowledge bases

  • Question 922:

    Vicus (team member) mentions they do not have enough market information to make proper decisions. Verna (agile facilitator) confirms it is because no one on the team understands the Asian market. Verna suggests to replace some team members, as they need to recruit team members that are familiar with the Asian market.

    What type of agile team would they be composing, with diverse skills and experience, who collectively have all the skills the team needs to fulfill its purpose?

    A. Cross-functional
    B. Project-oriented
    C. Virtual
    D. Organic

  • Question 923:

    The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

    A. Determine Budget.
    B. Baseline Budget.
    C. Control Costs.
    D. Estimate Costs.

  • Question 924:

    What type of project structure is a hierarchically organized depiction of the resources by type?

    A. Organizational breakdown structure (OBS)
    B. Resource breakdown structure (RBS)
    C. Work breakdown structure (WBS)
    D. Project breakdown structure (PBS)

  • Question 925:

    What is one of the main purposes of the project charter?

    A. Formal authorization of the existence of the project
    B. Formal acceptance of the project management plan
    C. Formal approval of the detailed project budget
    D. Formal definition of stakeholder roles and responsibilities

  • Question 926:

    A project manager is working on project cost management. The following information is current:

    Planned value = 30 Actual cost = 35 Earned value = 28

    Considering this data, which project indicator is correct?

    A. Schedule Variance (SV) = 2
    B. Cost Performance Index (CPI) = 0.80
    C. Schedule Performance Index (SPI) = 1.93
    D. Cost Variance (CV) = 7

  • Question 927:

    A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project.

    Which approach should the project manager select for the project?

    A. Adaptive
    B. Predictive
    C. Hybrid
    D. Kanban

  • Question 928:

    Which statement describes the relationship between Manage Quality process and Control Quality process?

    A. Manage Quality is all about following planned processes and procedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.
    B. Control Quality is all about following planned process and procedures for quality, while Manage Quality is about making sure that the product which is produced conforms to customer specifications.
    C. Manage Quality and Control Quality are the same.
    D. Manage Quality is part of Quality Management and Control Quality is a subset of the Stakeholder Management Process group.

  • Question 929:

    An output of the Develop Project Team process is:

    A. change requests
    B. team performance assessments
    C. project staff assignments
    D. project documents updates

  • Question 930:

    Which activity may occur at project or phase closure?

    A. Acceptance of deliverables
    B. Change requests
    C. Project management plan updates
    D. Benchmarking

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.