PMI CAPM Online Questions & Answers

  • Question 651:

    Which of the following is an output of the Distribute Information process?

    A. Project calendar
    B. Communications management plan
    C. Organizational process assets updates
    D. Project document updates

  • Question 652:

    In project management, a temporary project can be:

    A. Completed without planning
    B. A routine business process
    C. Long in duration
    D. Ongoing to produce goods

  • Question 653:

    A project team is working on a complex product and the work breakdown structure (WBS) is finalized. The team determines that the best approach is to use an adaptive delivery method and is now tasked with converting the WBS for adaptive delivery.

    How can the team manage the conversion of the existing WBS to an adaptive approach?

    A. Generate use cases for each WBS element and prepare a requirements document.
    B. Create themes for each WBS element and organize them into iterations for delivery.
    C. Organize the WBS into a set of related themes, epics, and user stories.
    D. Produce a release plan for each WBS element and organize them into iterations for delivery.

  • Question 654:

    During project selection, which factor is most important?

    A. Types of constraints
    B. Internal business needs
    C. Budget
    D. Schedule

  • Question 655:

    Outputs from constituent processes might be used as: A. Inputs to other processes.

    B. Proof of process completion.
    C. Identification of project tasks.
    D. Indicators to eliminate project redundancies.

  • Question 656:

    Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

    A. Estimate Costs
    B. Control Costs
    C. Determine Budget
    D. Plan Cost Management

  • Question 657:

    What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?

    A. Organizational process assets
    B. Enterprise environmental factors
    C. Project management processes
    D. Project scope management plan

  • Question 658:

    Product requirements specify a functionality that depends upon expertise that is unavailable internally. What process should be implemented to generate a make-or-buy decision?

    A. Conduct Procurements
    B. Plan Procurement Management
    C. Plan Risk Responses
    D. Plan Risk Management

  • Question 659:

    Which is one of the determining factors used to calculate CPI?

    A. EV
    B. SPI
    C. PV
    D. ETC

  • Question 660:

    Which of the following is example of communication tools and techniques?

    A. Conflict management
    B. Stakeholder mapping
    C. Advertising plan
    D. Developing team

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.