  • Question 521:

    Which schedule network analysis technique modifies the project schedule to account for limited resources?

    A. Human resource planning
    B. Fast tracking
    C. Critical chain method
    D. Rolling wave planning

  • Question 522:

    What should a project manager do to prepare a risk management plan in a project with a lot of technical uncertainty?

    A. Get expert judgment
    B. Count on personal experience
    C. Ask project sponsors
    D. Delay the project until technical uncertainty is clarified

  • Question 523:

    Which tools or techniques are used in the Plan Schedule Management process?

    A. Benchmarking, expert judgment, and analytical techniques
    B. Statistical sampling, benchmarking, and meetings
    C. Negotiations, pre-assignment, and multi-criteria decision analysis
    D. Expert judgment, analytical techniques, and meetings

  • Question 524:

    At the end of the project, what will be the value of SV?

    A. Positive
    B. Zero
    C. Negative
    D. Greater than one

  • Question 525:

    What is the key benefit of the Monitor Stakeholder Engagement process?

    A. Ensures that the informational needs of the project and its stakeholders are met through implementation and the development of artifacts
    B. Ensures that the project includes all the work required ?and only the work required ?to complete the project successfully
    C. Increases the probability and/or impact of positive risks, and decreases the probability and/or impact of negative risks or issues
    D. Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves

  • Question 526:

    Which of the following Project Communication Management processes uses performance reports as an input?

    A. Manage Stakeholder Expectations
    B. Report Performance
    C. Distribute Information
    D. Plan Communications

  • Question 527:

    What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

    A. $50
    B. $100
    C. $125
    D. $175

  • Question 528:

    The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

    A. Plan Human Resource Management.
    B. Acquire Project Team.
    C. Manage Project Team.
    D. Develop Project Team.

  • Question 529:

    Power, urgency, and legitimacy are attributes of which stakeholder classification model?

    A. Salience
    B. Influence/impact
    C. Power/interest
    D. Power/influence

  • Question 530:

    Which is an enterprise environmental factor?

    A. Marketplace conditions
    B. Policies and procedures
    C. Project files from previous projects
    D. Lessons learned from previous projects

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.