  • Question 441:

    When is a Salience Model used?

    A. In a work breakdown structure (WBS)
    B. During quality assurance
    C. In stakeholder analysis
    D. During quality control (QC)

  • Question 442:

    Who is responsible for reviewing change requests and approving or rejecting the change requests?

    A. Change control board
    B. Project manager
    C. Project management office
    D. Project sponsor

  • Question 443:

    The three processes of Project Cost Management are:

    A. Estimate Costs, Control Schedule, and Control Costs.
    B. Estimate Costs, Determine Budget, and Estimate Activity Resources.
    C. Determine Budget, Control Schedule, and Estimate Activity Resources.
    D. Estimate Costs, Determine Budget, and Control Costs.

  • Question 444:

    Which items are an output of the Perform Integrated Change Control process?

    A. Work performance reports
    B. Accepted deliverables
    C. Project management plan updates
    D. Organizational process assets

  • Question 445:

    A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

    A. Discussing with management
    B. Escalating to the sponsors
    C. Engaging regularly with stakeholders
    D. Engaging only with decision makers

  • Question 446:

    Given the following information, what is the schedule variance (SV) for this project?

    Early start date (ES): 16 weeks

    Actual time: 12 weeks Schedule performance index (SPI): 1.3

    A. 5
    B. 2
    C. 3
    D. 4

  • Question 447:

    Which tool is critical for the team to adapt to a high variability benefit project?

    A. Colocation
    B. Collaboration
    C. Flexibility
    D. Specialization

  • Question 448:

    Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

    A. Variance Analysis
    B. Define Scope
    C. Verify Scope
    D. Control Scope

  • Question 449:

    The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

    A. majority rule technique.
    B. nominal group technique.
    C. Delphi technique,
    D. idea/mind mapping technique.

  • Question 450:

    An input to the Perform Integrated Change Control process is:

    A. expert judgment
    B. seller proposals
    C. the project charter
    D. the project management plan

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.