  • Question 361:

    Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data.

    What kind of estimating is this?

    A. Bottom-up
    B. Three-point
    C. Parametric
    D. Analogous

  • Question 362:

    The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?

    A. Technical project management skills
    B. Time management skills
    C. Strategic and business management skills
    D. Leadership skills

  • Question 363:

    What are the three components of a work breakdown structure (WBS) dictionary? (Choose three.)

    A. List of stakeholders
    B. Description of risks
    C. List of resources
    D. Description of work
    E. Acceptance criteria

  • Question 364:

    An input to the Plan Cost Management process is:

    A. Cost estimates
    B. Resource calendars
    C. The project charter
    D. The risk register

  • Question 365:

    A project team identifies defects that will require a modification to a tool's functionality. What process should the project manager follow to obtain stakeholder buy-in?

    A. Control Schedule
    B. Perform Qualitative Risk Analysis
    C. Perform Integrated Change Control
    D. Control Scope

  • Question 366:

    High-level project risks are included in which document?

    A. Business case
    B. Risk breakdown structure
    C. Project charter
    D. Risk register

  • Question 367:

    While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

    A. Utilize the change control process.
    B. Crash the schedule to fix the defect.
    C. Leave the defect in and work around it.
    D. Fast-track the remaining development.

  • Question 368:

    When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

    A. Bottom-up
    B. Parametric
    C. Analogous
    D. Three-point

  • Question 369:

    The Monitoring and Controlling Process Group includes processes that:

    A. Establish the scope, objectives, and course of action of a project.
    B. Define a new project or a new phase of an existing project.
    C. Track, review, and regulate the progress and performance of a project.
    D. Complete the work defined in the project management plan.

  • Question 370:

    Which of the following processes are within the Initiating Process Group?

    A. Develop Project Management Plan and Identify Stakeholders
    B. Develop Project Management Plan and Plan Communications
    C. Develop Project Charter and Identify Stakeholders
    D. Develop Project Charter and Develop Project Scope Statement

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.