PMI CAPM Online Questions & Answers

  • Question 1291:

    How is the schedule variance calculated using the earned value technique?

    A. EV less AC
    B. AC less PV
    C. EV less PV
    D. AC less EV

  • Question 1292:

    Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

    A. Expert judgment.
    B. Analytical techniques.
    C. Earned value management.
    D. Group decision-making techniques.

  • Question 1293:

    Which of the following processes are part of the Project Integration Management Knowledge Area?

    A. Develop Project Management Plan, Collect Requirements, Create WBS
    B. Develop Project Management Plan, Control Scope, Develop Schedule
    C. Develop Project Charter, Define Scope, Estimate Costs
    D. Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

  • Question 1294:

    The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

    A. 1.33
    B. 2
    C. 0.75
    D. 0.5

  • Question 1295:

    Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

    A. Influencing
    B. Motivation
    C. Negotiation
    D. Trust building

  • Question 1296:

    In an agile or adaptive environment, when should risk be monitored and prioritized?

    A. Only during the Initiation and Closing phases
    B. During the Initiation and Planning phases
    C. During each iteration as the project progresses
    D. Throughout the Planning process group and retrospective meeting

  • Question 1297:

    Which output is the approved version of the time-phased project budget?

    A. Resource calendar
    B. Scope baseline
    C. Trend analysis
    D. Cost baseline

  • Question 1298:

    Which of these is true of a project schedule?

    A. Project Schedule Management processes are discrete and don't overlap
    B. Project schedules should typically allow for flexibility during the project
    C. Project schedules must always contain milestone lists and activity attributes
    D. Project schedules which are iterative can extend longer than four weeks

  • Question 1299:

    "Tailoring" is defined as the:

    A. effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.
    B. act of creating a project team with the specialized skills required to produce a required product or service.
    C. action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
    D. adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.

  • Question 1300:

    A reward can only be effective if it is:

    A. Given immediately after the project is completed.
    B. Something that is tangible.
    C. Formally given during project performance appraisals.
    D. Satisfying a need valued by the individual.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.