PMI CAPM Online Questions & Answers

  • Question 1031:

    How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

    A. Monitor project stakeholder relationships using engaging strategies and plans
    B. Send all project documents to stakeholders each time they are modified
    C. Schedule monthly meetings with the stakeholders, including team members
    D. Engage only with the project sponsors

  • Question 1032:

    Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

    A. Acquisition
    B. Negotiation
    C. Virtual team
    D. Pre-assignment

  • Question 1033:

    Which of the following project documents is an input to the Control Scope process?

    A. Vendor risk assessment diagram
    B. Risk register
    C. Requirements traceability matrix
    D. Area of responsibility summary

  • Question 1034:

    How can a project manager represent a contingency reserve in the schedule?

    A. Additional weeks of work to account for unknown-unknowns risks
    B. Task duration estimates of the best case scenarios
    C. Additional duration estimates in response to identified risks that have been accepted
    D. Milestones representing the completion of deliverables

  • Question 1035:

    The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

    A. Analysis
    B. Appetite
    C. Tolerance
    D. Response

  • Question 1036:

    When would resource leveling be applied to a schedule model?

    A. Before constraints have been identified
    B. Before it has been analyzed by the critical path method
    C. After it has been analyzed by the critical path method
    D. After critical activities have been removed from the critical path

  • Question 1037:

    Which of these is a hybrid contract?

    A. Cost plus award fee (CPAF)
    B. Firm fixed price (FFP)
    C. Fixed price incentive fee (FPIF)
    D. Time and material (TandM)

  • Question 1038:

    Change request status updates are an output of which process?

    A. Perform Integrated Change Control
    B. Direct and Manage Project Execution
    C. Close Project or Phase
    D. Monitor and Control Project Work

  • Question 1039:

    Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

    A. Budget plan
    B. Resource plan
    C. Scope plan
    D. Strategic plan

  • Question 1040:

    Assigned risk ratings are based upon:

    A. Root cause analysis.
    B. Risk probability and impact assessment.
    C. Expert judgment.
    D. Revised stakeholders' tolerances.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.