  • Question 31:

    An issue storage location was NOT found through the work center, bill of material(BOM) item, or material master. What determines whether the storage location can be derived from the production version?

    A. MRP group
    B. Plants parameters
    C. MRP controller
    D. MRP profile

  • Question 32:

    You want to create a production order from a planned order. What methods could you use? (Choose 2)

    A. Combined conversion
    B. Partial conversion
    C. Collective conversion
    D. Order release

  • Question 33:

    For which categories can you define BOMs in SAP S/4HANA? (Choose 2)

    A. Work Center
    B. Sales order
    C. Class
    D. Document Structure

  • Question 34:

    Which of the following is valid sequence of the main activities in production order processing? (Choose 2)

    A. Creation, availability check, release, material widrawal, confirmation
    B. Creation, release, printing, goods issue, confirmation, goods receipt
    C. Creation, printing, release, goods issue, confirmation, goods receipt
    D. Creation, release, settlement, goods issue, confirmation, goods receipt

  • Question 35:

    Which business processes are affected by setting in the order type-dependent parameters? (Choose 2)

    A. Intiate quality inspections.
    B. Select master data.
    C. Define integration to cost accounting.
    D. Implement engineering changes.

  • Question 36:

    In the Capacity Scheduling Table, which settings can you select for the planning strategy? (Choose 3)

    A. Planning mode
    B. Finiteness level
    C. Fixed pegging
    D. Direction E. Scheduling control

  • Question 37:

    In the Schedule Production app which setting can you make for the planning strategy?

    A. Fitness level
    B. Scheduling control
    C. Fixed pegging
    D. Direction
    E. Planning mode

  • Question 38:

    What detremines whatherthe planned independent requirements in MRP are consumed by other requrements?

    A. Consumption sequence procedure
    B. Requirements profile
    C. Order type
    D. Requirements type

  • Question 39:

    Which item statuses can you select inside a material BOM? (Choose 2)

    A. Service
    B. Sales
    C. Quality management
    D. Engineering

  • Question 40:

    What happens to this dependent requirement when you convert the planned order into a production order?

    A. They are converted into a schedule line.
    B. They are converted into a reservation.
    C. They are converted into a production order.
    D. They are converted into a planned order.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS422_2021 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.