SAP C_TS412_2021 Online Questions & Answers

  • Question 101:

    Which of the following data can be maintained in a standard network? Note: There are 3 correct answers to this question

    A. Document information records
    B. Internally processed activities
    C. Basic dates for activities
    D. Material components
    E. Relationships

  • Question 102:

    Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

    A. An activated Scheduling indicator in the control key of the internal processing activity
    B. Whether the work for the internal activity is greater than its duration
    C. The unit (for example, hour, day) of the field Normal Duration field of the activity
    D. The relationships between activity elements
    E. The factory calendar in the work center used for the internal processing activity

  • Question 103:

    Material

    How can the system activate requirements (such as reservations or purchase requisitions)?

    Note: There are 2 correct answers to this question

    A. Immediately, by saving the project
    B. Automatically, using the requirement date and the replenishment lead time
    C. Using a standard milestone activity
    D. When releasing a network or an activity

  • Question 104:

    Revenues and Payment

    Your customer wants to plans and post revenues for WBS elements.

    What is crucial for the implementation of revenues planning and posting for WBS elements?.

    A. At least one WBS element must be a billing element.
    B. The indicator "Project type" must be set to "Customer project".
    C. Revenue planning and billing must be activated in the corresponding network type.
    D. A sales order item has to be assigned to each WBS element used for revenue planning.

  • Question 105:

    How are earliest dates and latest dates of activities scheduled?

    A. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates
    B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling
    C. Earliest dates and latest dates are scheduled by forward scheduling
    D. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling

  • Question 106:

    Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.

    A. You can map a project using only one WBS or one network.
    B. You can also represent a project using a WBS and one or more networks.
    C. You can create a project based on a Activity.
    D. You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.

  • Question 107:

    Project Structures

    You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.

    What are the prerequisites? Note: There are 3 correct answers to this question

    A. A bill of material with sales views
    B. A material master with sales views
    C. Assignment between material and standard network
    D. Standard network with activities
    E. A production order

  • Question 108:

    You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?

    Note : there are 3 correct answer for this question.

    A. Project milestone
    B. Standard network
    C. Standard Project definition
    D. Project version.
    E. Project definition

  • Question 109:

    Revenues and Payment

    A customer use cross-company-code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?

    A. Settle the WBS element to the highest billing element before you do the result analysis.
    B. Split the project intdifferent project according to each company code.
    C. Change the project structure so that it correspond better to the company's organization structure.
    D. Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.

  • Question 110:

    Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

    A. Structure overview for budgets
    B. Hierarchical report on budget updates
    C. Cost element report on budget updates
    D. Line item report for budgets

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS412_2021 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.