SAP C_TPLM22_64 Online Questions & Answers

  • Question 21:

    You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined.

    What are the possible reasons for this?

    There are 2 correct answers to this question.

    Response:

    A. A work center has not been assigned to the activity.
    B. The work center does not contain any available capacity data.
    C. The wrong activity type category is entered in the activity.
    D. The indicator calculate capacity requirements is deactivated in the header of the network.

  • Question 22:

    Assume a scenario where deviations from the project plan occurred as a result of delivery problems, price fluctuations, and unforeseeable capacity bottlenecks. How do you ensure that claims resulting from deviations are prepared for

    contractual partners and submitted to them at suitable point of time? Please choose the correct answer.

    Response:

    A. Safety measures
    B. Status management
    C. Claim management
    D. Actions

  • Question 23:

    Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.

    Which of the following costs can be planned?

    There are 3 correct answers to this question.

    Response:

    A. Cost element level
    B. Each material
    C. Each internal activity
    D. Internal service

  • Question 24:

    To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element? There are 2 correct answers to this question.

    A. Billing element
    B. Cost element
    C. Account assignment element
    D. Pricing element

  • Question 25:

    What happens if the appended indicator is not set and an order is appended? Please choose the correct answer. Response:

    A. Order planned value is not added to the WBS planned value
    B. Order planned value is deducted from the WBS planned value
    C. Order planned value increases the WBS element planned value
    D. Order planned value is multiplied to the WBS element planned value

  • Question 26:

    Which ofthe following determines the available output of labor and machines within a certain time period? There are 2 correct answers to this question.

    A. Performance category
    B. Category in work center
    C. The capacity data in the work center
    D. The available capacity

  • Question 27:

    Which of the following scenario doesn't allow the plan value of the order to be added to the committed value of the WBS element until the order has the status released? Please choose the correct answer. Response:

    A. The funds commitment in plan indicators is set
    B. The funds commitment in plan indicator is not set
    C. The funds commitment in plan indicator is set to value less than 0
    D. The funds commitment in plan indicator also has status released

  • Question 28:

    Which of the following are used when you use the SAP Document Management System in Project System to assign document info records? There are 2 correct answers to this question. Response:

    A. WBS elements
    B. Activities
    C. Milestones
    D. Structures

  • Question 29:

    Which of the following are possible user exits that can be used while processing materials from the Project Systems? There are 3 correct answers to this question.

    A. CNEX0011 -- EXIT_SAPLCOMK_002
    B. CN015AFZ -- EXIT_SAPLCNFZ_003
    C. CNEX0009 -- EXIT_SAPLCOMK_001
    D. CNEXOO15 -- EXIT_SAPLCN10_002

  • Question 30:

    Most of the reports in the SAP Project System can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data? Please choose the correct the answer. Response:

    A. Hierarchical Reports
    B. Individual Overviews
    C. Reports by Cost Element
    D. Structure Overview

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.