  • Question 211:

    Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing? There are 2 correct answers to this question.

    A. Create a billing plan assigned to a sales order item.
    B. Set up percentage of completion for milestones.
    C. Activate indicator sales document date for milestones.
    D. Create a billing plan assigned to a WBS element.
    E. Activate milestone functions.

  • Question 212:

    Project System has its own Organizational structure, which can be a matrix structure.

    Please choose the correct answer.

    Response:

    A. True
    B. False

  • Question 213:

    Which type of confirmation allows you to enter the actual start and finish date, forecast finish date and forecast work in a tabular format? Please choose the correct answer.

    A. Group confirmation
    B. Single confirmation
    C. Individual confirmation
    D. Collective confirmation

  • Question 214:

    Which account assignment category is important for non-valuated project stock with WBS and sales order item?

    Please choose the correct answer.

    Response:

    A. E = quantities and values managed in the sales order item
    B. D = quantities managed using sales order item and values managed in projects
    C. G = plant stock, values managed using projects
    D. Q = quantities and values managed in projects

  • Question 215:

    Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis? Please choose the correct answer. Response:

    A. Trend technique
    B. Project technique
    C. Milestone technique
    D. Period indicator technique

  • Question 216:

    With reference to WBS scheduling, which of the following statements are FALSE? Please choose the correct answer. Response:

    A. In WBS scheduling, the activities which are assigned to the selected WBS elements are scheduled. In network scheduling on the other hand, all activities which belong to the network are scheduled.
    B. If you selected scheduling type 'WBS determines dates', the earliest start date of the activities is defaulted from the respective WBS elements in case of forward scheduling (or the latest finish date of the activities in case of backward scheduling).
    C. The execution of WBS scheduling consists steps: 1. Determining the initial dates (start dates for forward scheduling or finish dates for backward scheduling). 2. Transferring the dates of the activities into respective network headers and WBS elements.
    D. Activities which are not scheduled, but have relationships to activities involved in scheduling, are viewed as external activities. In this case, the dates of the external activity are taken into account as restricting dates.

  • Question 217:

    What are the various options available for creating a WBS BOM? There are 2 correct answers to this question. Response:

    A. Copying a Material BOM
    B. Copying a sales order BOM
    C. Copying other WBS BOM
    D. BOM copy function

  • Question 218:

    Which function of budgeting allows you to transfer any funds not used up in the previous fiscal year to the budget of the new fiscal year? Please choose the correct answer. Response:

    A. Budget release function
    B. Budget carry forward function
    C. Budget transfer function
    D. Budget Return function

  • Question 219:

    Which type of order is created at BOM level to cover requirements when a material shortage occurs in material planning?

    Please choose the correct answer.

    Response:

    A. Scheduled orders
    B. Procurement orders
    C. Planned orders
    D. Stock orders

  • Question 220:

    When you assign material components using the BOM transfer function, the system uses the Reference Point field in the BOM items and activities to establish a logical connection between which items? There are 2 correct answers to this

    question.

    Response:

    A. Individual BOM items
    B. Multiple BOM items
    C. Multi level BOM
    D. Network activities

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.