  • Question 141:

    Which scheduling calculates the latest start and finish dates for all activities? Please choose the correct answer.

    A. Backward scheduling
    B. Network based scheduling
    C. Forward scheduling
    D. Project based scheduling

  • Question 142:

    Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response? Please choose the correct answer. Response:

    A. Budget plan
    B. Availability control
    C. Time horizon
    D. Tolerance limit

  • Question 143:

    What should you call up to view all the information on an active or completed job that was scheduled in the scheduler in schedule manager? Please choose the correct answer. Response:

    A. Task list
    B. Job list
    C. Memory joggers
    D. Monitor

  • Question 144:

    Items procured through which of the following methods are not assigned to a stock segment and do not pass through a warehouse? Please choose the correct answer. Response:

    A. Indirectly
    B. Vendors
    C. Directly
    D. Non project stock items

  • Question 145:

    In which type of project stock costs from external procurement are posted directly to the stock-keeping WBS element when the goods or invoice are received? Please choose the correct answer. Response:

    A. No project stock
    B. Valuated project stock
    C. Non-valuated project stock
    D. Sales order project stock

  • Question 146:

    What are the prerequisites for automatic requirements grouping on the top WBS element of a project? There are 2 correct answers to this question. Response:

    A. The "project stock" indicator is set in the project definition (either valuated or non-valuated)
    B. The "Valuated project stock" indicator must be set in the project definition.
    C. The MRP group of the components must permit requirements grouping.
    D. The project must be released.
    E. The top-level WBS element must be released.

  • Question 147:

    What do you choose when creating a new network by copying an operative network? There are 3 correct answers to this question. Response:

    A. PS texts
    B. Relationships
    C. Milestones
    D. WBS elements

  • Question 148:

    What is the transaction code for editing the planning profile? Please choose the correct answer. Response:

    A. OPSS
    B. OPDS
    C. OPSB
    D. OPSC

  • Question 149:

    Which type of billing is generally used in plant engineering and construction projects? Please choose the correct answer. Response:

    A. Periodic billing
    B. Project billing
    C. Milestone billing
    D. Fixed billing

  • Question 150:

    Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format? Please choose the correct answer. Response:

    A. Individual confirmation
    B. Single confirmation
    C. Collective confirmation
    D. Group confirmation

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.