  • Question 101:

    A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend? There are 2 correct answers to this question. Response:

    A. Define Layout Detail Screen for WBS to specify customer-specific tabs.
    B. Define Create User-Defined Fields for WBS to specify the mandatory fields.
    C. Define Field Selection for WBS to specify the mandatory fields.
    D. Define Table Settings for WBS to specify customer-specific tabs.

  • Question 102:

    Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning? Please choose the correct answer.

    A. Customizing key
    B. Control key
    C. Scheduling key
    D. Confirmation key

  • Question 103:

    All the currency-dependent data in the Project System is managed in three different currencies in parallel. There are 3 correct answers to this question.

    A. Transaction currency
    B. Business Area Currency
    C. Controlling area currency
    D. Object Currency

  • Question 104:

    Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing? There are 2 correct answers to this question. Response:

    A. Activate milestone functions.
    B. Activate indicator sales document date for milestones.
    C. Create a billing plan assigned to a sales order item.
    D. Set up percentage of completion for milestones.
    E. Create a billing plan assigned to a WBS element.

  • Question 105:

    The determination of the settlement profile and result analysis key is based on WBS-operative indicators for which of the following? There are 2 correct answers to this question. Response:

    A. Billing element
    B. Settlement rule
    C. Operative rule
    D. Account assignment

  • Question 106:

    What are the three tables that are defined for order type in network costing? There are 3 correct answers to this question. Response:

    A. Each order type
    B. Each order type and plant
    C. Network profile
    D. Each plant

  • Question 107:

    Which of the following allows you to view project objects with key performance data for quick analysis and update the percentage complete for earned value calculations? Please choose the correct answer. Response:

    A. Project reporting
    B. Progress analysis work bench
    C. Project analysis Team View
    D. Project progress analysis

  • Question 108:

    The determination of the settlement profile and result analysis key is based on WBS-operative indicators for which of the following? There are 2 correct answers to this question.

    A. Account assignment
    B. Billing element
    C. Settlement rule
    D. Operative rule

  • Question 109:

    You are using the bottom-up scheduling scenario for a project containing WBS elements and networks. This means that ...

    There are 2 correct answers to this question.

    Response:

    A. ... basic dates of WBS elements are determined automatically.
    B. ... the networks determine the schedule.
    C. ... strict bottom-up planning is selected as the planning method.
    D. ... forward scheduling is selected as the scheduling type.
    E. ... the work breakdown structure determines the schedule.

  • Question 110:

    Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity? Please choose the

    correct answer.

    Response:

    Capacity planning board

    A. Work center planning board
    B. Project planning board
    C. Workforce planning board

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.