  • Question 1:

    You change an active project baseline and save it. Then, the system creates a new baseline. What are the statuses of the previous baseline and new baseline?

    A. Previous baseline: "active with pending changes" New baseline: "in planning"
    B. Previous baseline: "obsolete" New baseline: "in planning"
    C. Previous baseline: "obsolete" New baseline: "active"
    D. Previous baseline: "active with pending changes" New baseline: "in approval"

  • Question 2:

    In which phase of an implementation project do you set up your organizational structure in SAP Business ByDesign?

    A. Integrate and Extend
    B. Fine-Tune
    C. Scoping
    D. Prepare

  • Question 3:

    Which of the following documents in SAP Business ByDesign can you use to rectify a discrepancy in a released customer invoice? Note: There are 3 correct answers to this question.

    A. Cancellation invoice
    B. Rebate credit memo
    C. Correction invoice if available for the country
    D. Customer credit memo
    E. Recurring invoice template

  • Question 4:

    What is the correct priority and sequence to determine the cost rate in case of an internal service confirmation?

    A. First: Company-wide service cost rate Second: Group-wide service cost rate
    B. First: Resource cost rate Second: Company-wide service cost rate
    C. First: Company-wide service cost rate Second: Resource cost rate
    D. First: Resource cost rate Second: Group-wide service cost rate

  • Question 5:

    Which activities are available in the over the counter sales process? Note: There are 2 correct answers to this question.

    A. Managing receivables
    B. Creating quotes
    C. Managing warehouse tasks
    D. Outbound delivery

  • Question 6:

    Which of the following are prerequisites for managing inventory at a location (for internally- managed locationsonly)? Note: There are 3 correct answers to this question.

    A. Maintain a logistics model for the location.
    B. Create a storage control profile.
    C. Flag the location as 'Storage Location'.
    D. Flag a logistics area as 'Inventory Managed'.
    E. Create a location layout for the location.

  • Question 7:

    In which of the following ways can SAP Business ByDesign help you find a solution or report an incident? Note: There are 2 correct answers to this question.

    A. To better document an incident, users can add an attachment to provide more information.
    B. Users can create an incident and send it directly to the SAP.
    C. Users can search for a solution or report an incident from the screen on which the problem occurred.
    D. In the incident creation process, the search option considers company specific content but no community content.

  • Question 8:

    Which of the following prerequisites are needed to create a customer demand for a material that is planned in a project? Note: There are 2 correct answers to this question.

    A. The material must be ordered through a project purchase request
    B. The material must be a stocked material
    C. The material must be contained in a project stock order
    D. The material must be sold through the sales order that is linked to the project

  • Question 9:

    In the business scenario "Intercompany Project Time and Expenses" you want a consultant from the selling company to record travel expenses.

    In the buying company, you have already created a purchase order (PO) for the consultant in project "P". The system automatically creates a sales order (SO) and an intercompany project "IP" in the selling company. To enable travel expense recordings for the consultant, what is your next step?

    A. In the SO, create an item of type "Expense - time and material (project)" that is linked to the intercompany project "IP".
    B. In the PO, create a limit item that is account-assigned to the intercompany project "IP".
    C. In the PO, create a limit item that is account-assigned to a task in project "P".
    D. In the PO, create a service item with an expense product that is account-assigned to a task in project "P".

  • Question 10:

    Which of the following "Common Tasks" create tasks in the Physical Inventory work center? Note: There are 2 correct answers to this question.

    A. "New Product Count"
    B. "New Logistics Area Count"
    C. "Change of Stock'1
    D. "New Inventory Adjustment"

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_BYD01_1811 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.