  • Question 71:

    Which of the following tools are specific to the Data Management work stream?

    Note: There are 3 correct answers to this question

    A. SAP Landscape Transformation
    B. SAP Data Services
    C. SAP S/4HANA Migration Cockpit (for both SAP S/4HANA Cloud and SAP S/4HANA editions)
    D. SAP Roadmap Viewer
    E. SAP Solution Manager

  • Question 72:

    Which artifacts are part of the solution adoption workstream?

    There are 3 correct answers to this question

    A. Business transformation review (point of view)
    B. Project plan
    C. System go live announcement(order)
    D. Detailed design-business process

  • Question 73:

    When does the scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?

    Response:

    A. During the sprint review
    B. During the daily scrum meeting
    C. During the sprint retrospective
    D. During the user acceptance test

  • Question 74:

    Where can you find Data Migration templates?

    A. SAP roadmap viewer
    B. SAP S/4HANA Migration cockpit
    C. SAP best practices explorer
    D. SAP cloud appliance library

  • Question 75:

    In which phase do you verify that the SAP best practices content meets the customer's Business needs?

    A. Realize
    B. Deploy
    C. Prepare
    D. Explore

  • Question 76:

    In which phase will the customer develop a preliminary strategy for building A target operation and support organisational model?

    A. Discover phase
    B. Prepare phase
    C. Run phase
    D. Explore phase

  • Question 77:

    What is the purpose of a firm-up sprint?

    A. To perform string test
    B. To revise the release plan and sprint plan
    C. To run an end-to-end integration test
    D. To demonstrate functionality from previous sprints

  • Question 78:

    What is the difference between the "system conversion" and the "new implementation OF SAP S/4HANA transaction path?

    There are 2 correct option to this question.

    A. SSCUI's are used in system conversion for configuring SAP S/4HANA through the manage Your solution app
    B. In the realize phase, data is converted and not migrated for system conversion.
    C. There are different upgrade cycles
    D. In the realize phase, custom code is adjusted rather than developed for system conversion

  • Question 79:

    Working in an Agile approach, what should your planning look like at the Beginning of the realize phase?

    A. Project scope and planning are completed and final
    B. User stories are in a ready state for NO more than the first three sprints
    C. Go-live scope is fixed on the first of January the following year
    D. Timelines of the sprint may differ due to the workload

  • Question 80:

    Where can you find the integration content? There are 3 correct answers

    A. SAP cloud appliance library
    B. SAP Solution manger
    C. Cloud integration automatic service
    D. SAP API business hub
    E. SAP Best practices explorer

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_ACTIVATE13 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.