  • Question 31:

    What are the benefits of the SAP best practices? There are 3 correct answers to this question. Response:

    A. Fast time to value

    B. Predictable results

    C. Simple on-boarding to cloud

    D. Fixed organizational structure

    E. Reduced functional scope

  • Question 32:

    Which deliverable is specific to on-premise and NOT for the cloud? Please choose the correct answer. Response:

    A. Technical Design Solution

    B. Knowledge Transfer

    C. Adaptation Specification

    D. Learning Needs Analysis

  • Question 33:

    In which phase you execute the User Acceptance Test?

    Please choose the correct answer.

    Response:

    A. Build and Test

    B. Deploy

    C. Final Preparation

    D. Realize

  • Question 34:

    In which phase do you create a prioritized list of user requirements? Please choose the correct answer. Response:

    A. Realize

    B. Explore

    C. Prepare

    D. Deploy

  • Question 35:

    What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition?

    Please choose the correct answer.

    Response:

    A. SAP Best Practices

    B. Rapid prototyping

    C. Project team training

    D. Full project SCRUM

  • Question 36:

    In SAP Activate, what replaces the detailed Blueprint from ASAP? Please choose the correct answer. Response:

    A. Business Process Mapping

    B. Value Determination

    C. Custom Extension management

    D. Fit/Gap Workshops

  • Question 37:

    Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP

    S/4HANA On-Premise Edition?

    There are 3 correct answers to this question. Response:

    A. Operations impact analysis

    B. Custom code adjustment

    C. Delta configuration

    D. Development system migration

    E. Sandbox system migration

  • Question 38:

    What is the purpose of the SAP Activate Methodology?

    Please choose the correct answer.

    Response:

    A. To enable access to the SAP ecosystem

    B. To accelerate the initial implementation of SAP S/4HANA

    C. To provide end-to-end integrated application lifecycle management

    D. To manage project and solution documentation

  • Question 39:

    In what respect is SAP Activate Methodology different from the ASAP Methodology? Please choose the

    correct answer.

    Response:

    A. Supports cloud deployments

    B. Supports only new implementations

    C. Leverages iterative incremental build

    D. Includes Fit/Gap analysis instead of Blueprint

  • Question 40:

    Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile approach, what

    sequence of activities do you perform in the Explore Phase?

    Please choose the correct answer. Response:

    A. Conduct Solution Validation workshops

    B. Set reference value

    C. Prioritize initial backlog

    D. Conduct Delta Design workshops

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_ACTIVATE05 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.