SAP SAP Certified Associate C_ACTIVATE05 Questions & Answers

  • Question 21:

    Which key deliverable includes the development of RICEFW objects? Please choose the correct answer. Response:

    A. Development Build

    B. Enhancement Delivery

    C. Sprint Execution

    D. Custom Extensions Management

  • Question 22:

    Which activity helps the project team to add the user stories to the product backlog? Please choose the

    correct answer.

    Response:

    A. Planning the User Acceptance Test

    B. Preparing a Project Schedule

    C. Conducting the Solution Validation

    D. Assessing Project Risks

  • Question 23:

    Which criterion does the Product Owner use to sequence the product backlog? Please choose the correct

    answer.

    Response:

    A. Resource availability

    B. Complexity

    C. Business priority

    D. Relative effort

  • Question 24:

    In Which phase does the Transition to Operations work stream start? Please choose the correct answer. Response:

    A. Explore

    B. Realize

    C. Deploy

    D. Prepare

  • Question 25:

    What technique helps agile project teams to prioritize a large, flat backlog? Please choose the correct

    answer.

    Response:

    A. Fit/Gap Analysis

    B. User Story Mapping

    C. Retrospective

    D. Planning Poker

  • Question 26:

    In which SAP Activate methodology phase does the team complete the Integration Validation? Please

    choose the correct answer.

    Response:

    A. Explore

    B. Realize

    C. Deploy

    D. Prepare

  • Question 27:

    Your project is performing some high-level planning for a System Conversion journey from SAP Business

    Suite to SAP S/4HANA on-premise edition. What is the correct sequence of selected key deliverables

    across the project phases?

    Please choose the correct answer.

    Response:

    A. Code adjustment

    B. Detailed System Assessment

    C. Production Readiness Check

    D. Validation of Migration

  • Question 28:

    How are the build and test tasks planned and executed in the Realize phase? Please choose the correct

    answer.

    Response:

    A. By using the sprint backlog list as input for each iteration.

    B. By executing regression tests after each iteration

    C. With Q-Gates for sign off after each iteration

    D. By using incremental build in fixed-scope iteration

  • Question 29:

    Response:

    A. Ask questions

    B. Update Key Deliverable wikis

    C. Tweet questions

    D. Comment on documents

  • Question 30:

    In which phase of the SAP Activate methodology does the team complete the Transformation Planning?

    Please choose the correct answer.

    Response:

    A. Deploy

    B. Explore

    C. Prepare

    D. Realize

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_ACTIVATE05 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.