Exam Details

  • Exam Code
    :C_ACTIVATE05
  • Exam Name
    :SAP Certified Associate - SAP Activate Project Manager
  • Certification
    :SAP Certified Associate
  • Vendor
    :SAP
  • Total Questions
    :80 Q&As
  • Last Updated
    :May 15, 2024

SAP SAP Certified Associate C_ACTIVATE05 Questions & Answers

  • Question 11:

    What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition? Please

    choose the correct answer.

    Response:

    A. Start with executable content

    B. Limited involvement of business stakeholders

    C. Waterfall approach

    D. Design-based

  • Question 12:

    In which phase do you verify that the SAP Best Practice solution scenarios meet the business needs of the

    customer?

    Please choose the correct answer. Response:

    A. Explore

    B. Deploy

    C. Realize

    D. Prepare

  • Question 13:

    Which new project roles are introduced with the SAP Activate Agile methodology?

    There are 2 correct answers to this question.

    Response:

    A. SCRUM Master

    B. Product Owner

    C. Integration Lead

    D. Design Thinking Coach

  • Question 14:

    Which of the following is a Key Deliverable of the Prepare phase? Please choose the correct answer. Response:

    A. Solution Scope and Value Determination

    B. Change Impact Analysis and Communication Plan

    C. Baseline Build

    D. Release and Sprint Plan

  • Question 15:

    Which activities are part of the Application: Solution Adaption work stream of SAP Activate for new

    implementations?

    There are 3 correct answers to this question. Response:

    A. Value Audits

    B. Production Support Plan

    C. Value Determination

    D. Change Management Plan

    E. Scope Validation

  • Question 16:

    What is SAP Activate?

    Please choose the correct answer.

    Response:

    A. A step-by-step instruction on how to remove from SAP best practices to your custom solution

    B. A methodology for each of the deployment modes (cloud , on-premise, hybrid)

    C. A bundle of ASAP , SAP Launch , and Rapid Deployment Solutions

    D. A combination of SAP best practices , methodology, and guided configuration

  • Question 17:

    Which content packages are available in the SAP Package Library? There are 2 correct answers to this question.

    Response:

    A. SAP Activate Methodology

    B. SAP Best Practices

    C. Solution Builder

    D. Rapid Deployment Solutions

  • Question 18:

    Who determines the tasks that are required to complete the committed backlog items in a sprint? Please

    choose the correct answer.

    Response:

    A. Project Manager

    B. Product Owner

    C. Project Team

    D. SCRUM Master

  • Question 19:

    What are the responsibilities of the Project Team on level 4 in the picture below? There are 2 correct

    answers to this question.

    Response:

    A. Set Project policy, standards and oversight

    B. Set business priorities, goals and objectives

    C. Identify and resolve issues and risks

    D. Perform status reporting and communication

  • Question 20:

    In which phase of the SAP Activate Methodology does the team complete the System Assessment?

    Please choose the correct answer.

    Response:

    A. Deploy

    B. Explore

    C. Prepare

    D. Realize

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_ACTIVATE05 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.