Question 41:
What is the purpose of the option clusternode yes?
A. It uses a cluster node as proxy node for backups. B. It configures IBM Tivoli Storage Manager (TSM) to back up the primary node first. C. It allows multiple TSM clients to backup a single disk resource. D. It specifies how the TSM Backup-Archive client manages cluster drives.
C. It allows multiple TSM clients to backup a single disk resource.
Question 42:
Which two inputs are required to define a spoke server with the IBM Tivoli Storage Manager V7.1 Operations Center?
A. Hub server port B. Hub server address C. Spoke server address D. System admin password E. Spoke server communication method
C. Spoke server address D. System admin password
Question 43:
What is the purpose of the db2 ? SQL2581 command from the IBM DB2 (DB2) command line?
A. It explains the SQL error 2581. B. It executes SQL statement 2581 immediately. C. It verifies that the DB2 SQL processor is at version 2581. D. It lists the last 2581 SQL commands that were executed.
A. It explains the SQL error 2581.
Question 44:
Under which two circumstances is a directory backup performed?
A. Only for selective backup. B. Directory permissions changes. C. A directory was not previously backed up. D. If any file within the directory has changed. E. If DIRMC is specified in the client options file.
C. A directory was not previously backed up. D. If any file within the directory has changed.
Question 45:
What are two reasons to use the enablededupcache client option?
A. To improve client-side compression. B. To expedite the restore of deduped objects. C. To cache dedupe hits on the Tivoli Storage Manager (TSM) server. D. So that the client keeps a copy of the data extents that already exist on the TSM server. E. So that the client does not have to check with the server to determine what needs to be sent.
A. To improve client-side compression. E. So that the client does not have to check with the server to determine what needs to be sent.
Question 46:
When upgrading from IBM Tivoli Storage Manager (TSM) V5to TSM V7.1, which two steps should be performed before starting the upgrade process?
A. Back up the copypool data. B. Uninstall the V5 server and client. C. Back up the V5 database and configuration files. D. Install the database configuration tool (DB2CNFG). E. Install the upgrade utilities package (DSMUPGRD).
C. Back up the V5 database and configuration files. E. Install the upgrade utilities package (DSMUPGRD).
Question 47:
An IBM Tivoli Storage Manager administrator has 123 nodes backing up to the server. Over several weeks the administrator notices that more volumes are being used up even when the amount of data has not increased significantly. What are two reasons why this would happen?
A. Collocation by volume group for LTOPOOL B. Collocation by node for LTOTAPE storage pool is set. C. Reclamation threshold for LTOTAPE storage pool is set to 1. D. Reclamation threshold for LTOTAPE storage pool is set to 50. E. Reclamation threshold for LTOTAPE storage pool is set to 100.
A. Collocation by volume group for LTOPOOL D. Reclamation threshold for LTOTAPE storage pool is set to 50.
Question 48:
Which statement is true regarding group backup?
A. Group backups cannot be exported. B. Objects in the group can expire individually. C. A group backup supports full and differential backup. D. Full and incremental backup is supported by a group backup.
D. Full and incremental backup is supported by a group backup.
Question 49:
What is the purpose of the duration option in the expire inventory command?
A. It specifies how often the process should run. B. It specifies how long to keep archived objects before they can be expired. C. It specifies the maximum number of minutes for the expiration process to run. D. It specifies how long the objects must reside in the storage pool before they can be expired.
C. It specifies the maximum number of minutes for the expiration process to run.
Question 50:
How can data of a specific node be deleted from a copy storage pool?
A. Delete the copy storage pool and recreate it from the primary storage pool. B. Use the command delete nodedata to delete this specific nodes data. C. Move this node's data with the move nodedata function to separate tapes and delete this volumes with discard=yes. D. Move this node's data with the move nodedata function to a separate copy storage pool and delete this storage pool with discard=yes.
C. Move this node's data with the move nodedata function to separate tapes and delete this volumes with discard=yes.
Nowadays, the certification exams become more and more important and required by more and more
enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare
for the exam in a short time with less efforts? How to get a ideal result and how to find the
most reliable resources? Here on Vcedump.com, you will find all the answers.
Vcedump.com provide not only IBM exam questions,
answers and explanations but also complete assistance on your exam preparation and certification
application. If you are confused on your C2010-511 exam preparations
and IBM certification application, do not hesitate to visit our
Vcedump.com to find your solutions here.