  • Question 611:

    An output of the Plan Quality Management process is:

    A. A process improvement plan,
    B. Quality control measurements.
    C. Work performance information,
    D. The project management plan.

  • Question 612:

    Analytical techniques are a tool and technique of which process in Project Procurement Management?

    A. Plan Procurement Management
    B. Control Procurements
    C. Conduct Procurements
    D. Close Procurements

  • Question 613:

    The process to ensure that appropriate quality standards and operational definitions are used is:

    A. Plan Quality.
    B. Perform Quality Assurance.
    C. Perform Quality Control.
    D. Total Quality Management.

  • Question 614:

    A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

    A. Efficient
    B. Effective
    C. Push
    D. Pull

  • Question 615:

    Which of the following documents allows the project manager to assess risks that may require near term action?

    A. Probability and impact matrix
    B. Contingency analysis report
    C. Risk urgency assessment
    D. Rolling wave plan

  • Question 616:

    A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

    A. Cost Plus Incentive Fee (CPIF).
    B. Fixed Price Incentive Fee (FPIF).
    C. Cost Plus Award Fee (CPAF).
    D. Fixed Price with Economic Price Adjustment (FP-EPA).

  • Question 617:

    Which organizational process assets update is performed during the Close Procurements process?

    A. Procurement audit
    B. Lessons learned
    C. Performance reporting
    D. Payment requests

  • Question 618:

    A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

    A. US$S000
    B. US$9500
    C. US$10,000
    D. US$12,500

  • Question 619:

    An input of the Control Schedule process is the:

    A. resource calendar.
    B. activity list.
    C. risk management plan.
    D. organizational process assets.

  • Question 620:

    Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

    A. The Delphi technique
    B. Nominal group technique
    C. Affinity diagram
    D. Brainstorming

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.