GAQM APM-001 Online Questions & Answers

  • Question 481:

    Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

    A. Critical path method
    B. Critical chain method
    C. Resource leveling
    D. Schedule network analysis

  • Question 482:

    A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

    A. risk management plan
    B. human resource management plan
    C. scope management plan
    D. procurement management plan

  • Question 483:

    When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

    A. Bottom-up
    B. Parametric
    C. Analogous
    D. Three-point

  • Question 484:

    The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

    A. stakeholder management strategy.
    B. communications management plan.
    C. stakeholder register.
    D. performance report.

  • Question 485:

    Which of the following types of a dependency determination is used to define the sequence of activities?

    A. Legal
    B. Discretionary
    C. Internal
    D. Resource

  • Question 486:

    In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

    A. Technical approach
    B. Technical capability
    C. Business size and type
    D. Production capacity and interest

  • Question 487:

    Which of the following tools and techniques is used in the Verify Scope process?

    A. Inspection
    B. Variance analysis
    C. Expert judgment
    D. Decomposition

  • Question 488:

    Which of the following investigates the likelihood that each specific risk will occur?

    A. Risk register
    B. Risk audits
    C. Risk urgency assessment
    D. Risk probability and impact assessment

  • Question 489:

    Which type of dependency is contractually required or inherent in the nature of the work?

    A. External
    B. Lead
    C. Discretionary
    D. Mandatory

  • Question 490:

    The process of identifying the stakeholders' information needs is completed during:

    A. Plan Communications.
    B. Manage Stakeholder Expectations.
    C. Stakeholder Analysis.
    D. Identify Stakeholders.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.