  • Question 201:

    The Define Scope process is in which of the following Process Groups?

    A. Initiating
    B. Planning
    C. Monitoring and Controlling
    D. Executing

  • Question 202:

    Lessons learned documentation is gathered during which of the following Project Management Process Groups?

    A. Planning
    B. Executing
    C. Closing
    D. Initiating

  • Question 203:

    What is the responsibility of the project manager and the functional manager respectively?

    A. Oversight for an administrative area; a facet of the core business
    B. Achieving the project objectives; providing management oversight for an administrative area
    C. A facet of the core business; achieving the project objectives
    D. Both are responsible for achieving the project objectives.

  • Question 204:

    Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

    A. Stakeholder register
    B. Scope management plan
    C. Stakeholder management plan
    D. Project charter

  • Question 205:

    Which action should a project manager take to ensure that the project management plan is effective and current?

    A. Conduct periodic project performance reviews.
    B. Identify quality project standards.
    C. Follow ISO 9000 quality standards.
    D. Complete the quality control checklist.

  • Question 206:

    Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

    A. Requirements traceability matrix
    B. Work breakdown structure (WBS) dictionary
    C. Requirements management plan
    D. Requirements documentation

  • Question 207:

    The following chart contains information about the tasks in a project.

    Based on the chart, what is the schedule performance index (5PI) for Task 4?

    A. 0.83
    B. 0.9
    C. 1.11
    D. 1.33

  • Question 208:

    Which baselines make up the performance measurement baseline?

    A. Scope baseline, cost baseline, and schedule baseline
    B. Scope baseline, project management baseline, and quality baseline
    C. Cost baseline, schedule baseline, and risk baseline
    D. Cost baseline, project management baseline, and schedule baseline

  • Question 209:

    An input to the Plan Procurement Management process is:

    A. Source selection criteria.
    B. Market research.
    C. A stakeholder register.
    D. A records management system.

  • Question 210:

    Which Process Group includes the Manage Stakeholder Engagement process?

    A. Executing
    B. Planning
    C. Monitoring and Controlling
    D. Initiating

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.