  • Question 161:

    An output of the Create WBS process is:

    A. Scope baseline.
    B. Project scope statement.
    C. Organizational process assets.
    D. Requirements traceability matrix.

  • Question 162:

    An input of the Create WBS process is:

    A. requirements documentation.
    B. scope baseline.
    C. project charter.
    D. validated deliverables.

  • Question 163:

    Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

    A. Crashing
    B. Fast tracking
    C. Leads and lags adjustment
    D. Parallel task development

  • Question 164:

    Which of the following is a strategy to deal with positive risks or opportunities?

    A. Mitigate
    B. Transfer
    C. Exploit
    D. Avoid

  • Question 165:

    Which of the following is a tool or technique used in the Acquire Project Team process?

    A. Networking
    B. Training
    C. Negotiation
    D. Issue log

  • Question 166:

    Which process involves developing an approximation of the monetary resources needed to complete project activities?

    A. Estimate Costs
    B. Control Costs
    C. Determine Budget
    D. Plan Cost Management

  • Question 167:

    Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

    A. Verified deliverables.
    B. Validated deliverables.
    C. Acceptance criteria.
    D. Activity resource requirements.

  • Question 168:

    As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

    A. BAC
    B. EAC
    C. ETC
    D. WBS

  • Question 169:

    Which is used to solicit proposals from prospective sellers?

    A. Procurement statement of work
    B. Resource calendars
    C. Procurement document
    D. Independent estimates

  • Question 170:

    A complete set of concepts, terms, and activities that make up an area of specialization is known as:

    A. a Knowledge Area
    B. a Process Group
    C. program management
    D. portfolio management

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.