  • Question 151:

    What are examples of relevant inputs to Project Plan preparation?

    A. PMBok.

    B. Customer RFQ and Customer Implementation Requirements (priority, site specifications), besides the sub plans that PM considers relevant.

    C. Cost Plan, Schedule and Quality Plan.

    D. All inputs defined in the NSN Project Plan Template.

  • Question 152:

    What is the basic source of information for the development of the Quality Plan?

    A. Project quality and acceptance requirements stated in the current customer contract.

    B. Equipment installation manuals.

    C. Templates from NSN PM Compass.

    D. Experience from previous projects executed with the same Customer.

  • Question 153:

    What are the correct planning horizons for short-term and long-term resource planning?

    A. Short-term: 2 weeks, long-term: 6 months

    B. Short-term: 4 weeks, long-term: 8 months

    C. Short-term: 8 weeks, long-term: 13 months

    D. Short-term: 12 weeks, long-term: 12 months

  • Question 154:

    How would you handle performance problems related to RAN frequency planning in a project where customer is responsible for Network Planning?

    A. Request NPO resources to your project and start troubleshooting.

    B. Do nothing, the performance problems are customer's responsibility in this case.

    C. Request implementation teams to go to the field, make test calls and help the customer to identify where the problem is most critical.

    D. Request an NSN NPO Solution Consultant to meet the customer for evaluating a potential up selling opportunity.

  • Question 155:

    What would be the preferred course of actions when you find out that the project Gross Margin is showing a lower figure in PRS(Profitability Reporting System) than what you expected?

    A. Escalate the problem to the CT Head.

    B. Request the CPM to prepare a detailed presentation about project costs.

    C. Invite the CPM and Project FandC to identify the deviations and review if cost and revenue have been correctly reported in PRS according to the Demand Plan assumptions and Project Cost calculations.

    D. Start a cost reduction plan and reduce headcount.

  • Question 156:

    When must a Change Management process be initiated?

    A. When there is a significant change in the scope of the project.

    B. When the Customer sends a formal request for additional Scope of Work.

    C. When the CT Head acknowledges that the customer will accept to negotiate the changes in the scope of the contract.

    D. Whenever the project execution requires services or materials different from those agreed in the contractual scope of work.

  • Question 157:

    How should integration engineer resources be planned for the RA network integration?

    A. Include an estimation of local resources in the project headcount.

    B. Prepare an RFQ for external suppliers with the support of Procurement.

    C. Include the input from GNIC into your service cost estimation.

    D. Communicate the need of integration engineers for your project during the MRM (Monthly Resource Meeting).

  • Question 158:

    When can the project management plan be modified?

    A. Up to the start of project execution, from then on the project management plan must be frozen as a baseline for future reference.

    B. In case the scope of work has changed.

    C. Over time during the project as it has at any time to reflect the latest status of the agreed practices, processes and responsibilities.

    D. When the PM receives the handover from Sales do Delivery.

  • Question 159:

    Which statement describes BEST the purpose of a project management plan ?

    A. The project management plan defines in detail how the project is going to deliver the contracted scope.

    B. The project management plan nominates the Project Manager and describes the Scope of Work.

    C. The project management plan documents the handover from sales to execution.

    D. The project management plan is used to get management approval for project execution.

  • Question 160:

    During the bidding phase, what type of support can be provided by the PPM (Project Procurement Manager)?

    A. Ensure cost efficient, qualified and compliant 3rd party solutions for the customer project.

    B. None. PPM is responsible for negotiating the 3rd party contracts after the deal with the customer is closed.

    C. Prepare training plans to develop 3rd Party competence level.

    D. Proactively develop the supply chain for required materials.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Nokia exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your SDM_2002001050 exam preparations and Nokia certification application, do not hesitate to visit our Vcedump.com to find your solutions here.