  • Question 171:

    Which describes a risk event?

    A. The area of uncertainty in terms of the threat or opportunity

    B. The derivation or sources of a potential risk to the project

    C. The achievement of a milestone on the Project Plan

    D. The sequence of events and actions that will be put in place if a risk occurs

  • Question 172:

    During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?

    A. Project Product Description

    B. Business Case

    C. Project Brief

    D. Project mandate

  • Question 173:

    Which is a purpose of a Lessons Report?

    A. Improve the project management method for future projects

    B. Detail open issues and risks that need to be managed after the project has closed

    C. Compare the actual performance of the final stage against its plan

    D. Provide a summary of the benefits realized during the project

  • Question 174:

    Identify the missing words in the following sentence. A Change Authority may be given a [?] to enable it to finance new requirements.

    A. change budget

    B. cost tolerance

    C. risk budget

    D. scope tolerance

  • Question 175:

    How is a Benefits Review Plan used in the Closing a Project process?

    A. Checked for inclusion of activities to confirm those benefits which cannot be measured until after project closure

    B. To capture the baseline measures against which to assess benefits

    C. To capture side-effects (beneficial or adverse) identified during post-project benefits reviews

    D. To gain approval for the post-project activities and transfer responsibility to corporate or programme management

  • Question 176:

    Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.

    A. Change

    B. Plans

    C. Progress

    D. Risk

  • Question 177:

    Which is a responsibility of a Team Manager?

    A. Producing Highlight Reports for the Project Manager

    B. Reviewing the status of the stage

    C. Setting Work Package tolerances

    D. Ensuring delivery of products in the Managing Product Delivery process

  • Question 178:

    What theme provides all management levels within the project management team with mechanisms for monitoring and control?

    A. Progress

    B. Change

    C. Organization

    D. Quality

  • Question 179:

    What do acceptance criteria identify?

    A. The approach that will be used to prove whether the project's products have been completed

    B. A measureable improvement resulting from a project outcome

    C. The measureable definitions of the attributes for a set of products to be acceptable to key stakeholders

    D. The project controls set up during the process Initiating a Project

  • Question 180:

    Which should be funded by a change budget?

    A. Increase in agreed scope

    B. Increase in agreed scope

    C. Increase in agreed scope

    D. Handover activities

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.