Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional
  • Certification
    :PMI Certification
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :May 12, 2024

PMI PMI Certification PMI-SP Questions & Answers

  • Question 41:

    You are the project manager for the NHQ project. The management has reminded you that you must not allocate any project team member for more than 25 hours per work week on your project. This policy is because your organization is in a weak matrix and the project team members are on several projects at once within the organization. The 25-hour limit per resource is an example of which one of the following?

    A. Expert judgment

    B. Enterprise environmental factor

    C. Resource limitation

    D. Organizational process asset

  • Question 42:

    You are the project manager for your organization. Your current project has a schedule variance of - $37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance?

    A. Your project is likely to be late and over budget.

    B. Your project is performing well.

    C. Your project has a planned value of $600,000.

    D. Your project is six percent off schedule and has a considerable schedule variance.

  • Question 43:

    You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are up posed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule variance?

    A. 10 percent

    B. -$48,654

    C. -$225,000

    D. 0.98

  • Question 44:

    You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?

    A. Risk management plan

    B. Schedule management plan

    C. Risk register

    D. Activity attributes

  • Question 45:

    Jeff is the project manager of the GHY Project for his organization. He has created the project network diagram as shown in the figure:

    Management is reviewing the network diagram, and they are concerned about the latest date that Activity I can finish. What is the latest day Activity I can finish without affecting the project end date?

    A. Day 20

    B. Day 22

    C. Day 17

    D. Day 19

  • Question 46:

    You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your schedule variance for this project?

    A. $11,667

    B. 1.02

    C. $7,000

    D. $-111,750

  • Question 47:

    You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should you tell management?

    A. $566,305

    B. $787,504

    C. $1,312,504

    D. $733,456

  • Question 48:

    Della works as a project manager for BlueWell Inc. She has asked her assistant Beth to provide activity duration estimate for an activity. Beth provides Della the following estimate chart:

    What will be the activity duration according to the PERT three-point analysis?

    A. 19

    B. 24

    C. 29

    D. 46

  • Question 49:

    John works as the project manager for Blue Well Inc. He is identifying the phases within the scope of work for the project plan. Which of the following can be categorized as a project phase? Each correct answer represents a complete solution. Choose all that apply.

    A. Concrete

    B. Pre-construction

    C. Engineering

    D. Conceptual engineering

  • Question 50:

    Gary is the project manager of the NGH project for his organization. He and the project team have created the initial WBS. Before Gary and the project team begin creating the activity list, Gary wants the project team to help him create a unique numbering system for the deliverables identified in the WBS. What numbering system can Gary and the project team apply to the WBS to identify the components of the WBS?

    A. Code of accounts

    B. Chart of accounts

    C. Component numbering

    D. Activity linkage sequencing

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.