Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional
  • Certification
    :PMI Certification
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :May 12, 2024

PMI PMI Certification PMI-SP Questions & Answers

  • Question 11:

    You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's planned value?

    A. $2,025,000

    B. There is not enough information to know

    C. $4,500,000

    D. $2,250,000

  • Question 12:

    You are the project manager of the NHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day for the early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but you must be careful not to increase project risk beyond an acceptable level of risk exposure. Which of the following approaches is most likely to increase project risk?

    A. Using the critical chain method

    B. Crashing

    C. Adding leads to the project work

    D. Fast tracking

  • Question 13:

    Which of the following is NOT an output of the control schedule process?

    A. Organizational process assets

    B. Change requests

    C. Project termination request

    D. Project document updates

  • Question 14:

    A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Choose three.

    A. Performance control

    B. Execution scheduling

    C. Leadership

    D. Feasibility planning

  • Question 15:

    What formula would you use if your project had a BAC of $450,000, you have spent $191,000, and you are 40 percent complete though you are supposed to be 55 percent done and management wants to know your project's schedule performance index?

    A. ($450,000 - $180,000) / ($450,000 - $191,000)

    B. $450,000 - $477,500

    C. $180,000 / $247,500

    D. $180,000 - $247,500

  • Question 16:

    Which of the following characteristics of conflict and the conflict management process should be recognized by the project managers while handling conflict in a team environment? Each correct answer represents a complete solution. Choose all that apply.

    A. Conflict resolution should focus on issues, not personalities.

    B. Conflict is natural and forces a search for alternatives.

    C. Openness resolves conflict.

    D. Conflict is an individual issue.

  • Question 17:

    You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what your schedule variance is. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is the schedule variance for this project?

    A. -$45,789

    B. -$56,790

    C. There is not enough information to know.

    D. -$30,268

  • Question 18:

    You are the project manager of the GHQ Project. You are working with your project team to create the project network diagram. You have created the PND and are identifying the critical path with your team using your project management information system. All of the activities on the critical path are showing in red in the software that you are using to evaluate the critical path. What are schedule activities on the critical path called?

    A. Critical activities

    B. Action items

    C. High alert activities

    D. Red rated activities

  • Question 19:

    Maurice is the project manager of the NHQ Project and his project team has just finished the project activities. The quality control team reports that the project deliverables are perfect. The only thing left to in the project is to verify scope. This process will be performed by the project stakeholders. Maurice is required to submit a final project report and report on the project performance. Maurice's project had a budget of $234,000 but the project spent $245,000. In the final report management wants to know the project's cost performance index (CPI). What value should Maurice report?

    A. -$11,000

    B. .96

    C. There is not enough information to know.

    D. 1

  • Question 20:

    Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?

    A. -$98,217.78

    B. -$44,198

    C. $441,025.64

    D. $243,219.78

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.