Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional
  • Certification
    :PMI Certification
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :May 12, 2024

PMI PMI Certification PMI-SP Questions & Answers

  • Question 31:

    You work as a project manager for Honeywell Inc. You have been distributing performance information, including status reports, progress measurement, and forecasts to various stakeholders. A trainee of this company wants to know what are the inputs for generating performance reports. Which of the following are the necessary inputs? Each correct answer represents a part of the solution. Choose two.

    A. Variance analysis

    B. WPM

    C. WPI

    D. Change request

  • Question 32:

    Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms need to be primed and painted. Before each room can be painted, the primer must cure for twenty-four hours. Fred has arranged these tasks with a finish to start relationship between the priming and the painting. What else should Fred do to account for the twenty-four hours of cure time?

    A. Fred should add twenty-four hours of lead time to each of the 456 rooms painting activity to account for the primer's curing time.

    B. Fred should add twenty-four hours of lag time to each of the 456 rooms painting activity to account for the primer's curing time.

    C. Fred should add an intermediary task with a duration of twenty-four hours.

    D. Fred should schedule all 456 hotels rooms to be primed first and then schedule all 456 rooms to be painted to ensure time for the curing.

  • Question 33:

    Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below:

    MeasurementsValues BCWP (or EV) 425 BCWS (or PV) 400 ACWP (or AC) 510 What is the schedule performance index (SPI) of the project at the current point of time?

    A. 1.082

    B. 0.88

    C. 1.0625

    D. 0.96

  • Question 34:

    You work as a stakeholder for ABC Inc. You are on an important feature of a project that appears too difficult to execute. Issues like acceptable type of bugs and number of bugs for user acceptance seem to have affected the project. What is the rate of risk factor in such a situation?

    A. Risk factors are rated high.

    B. Risk factors are rated low.

    C. Risk factors are rated medium-high.

    D. Risk factors are rated medium.

  • Question 35:

    You are the project manager for your organization. You are coaching Allen, a junior project manager, on how the details of the project's critical path are calculated. Examine the figure given below:

    What is the critical path of this project?

    A. ABEHJ

    B. ACFGJ

    C. ADGJ

    D. ACFIJ

  • Question 36:

    Harry is the project manager of a large network installation project. This project requires Harry to add network cable to each office and cubicle of a 14-story office building. Harry will receive a bonus for good time and cost performance in this project. What law of economics would prevent Harry from exponentially adding labor to the project work in an effort to complete the work in a very small amount of time?

    A. Parkinson's Law

    B. Law of Diminishing Returns

    C. Law of Economics

    D. Moore's Law

  • Question 37:

    You are the project manager for the NQQ Project for your organization. You and the project team are creating the activity list for the NQQ Project. You have instructed the project team members that they should include an activity identifier

    and a scope of work description for each activity in the activity list.

    Why is this information needed?

    A. To track the work to the project requirements

    B. To maintain profit and loss statements for the project

    C. To help the project team understand what work is required to be completed

    D. To communicate the work to be completed to the project stakeholders

  • Question 38:

    You work as a Project Manager for Media Perfect Inc. Several projects are running under your supervision. Rick, team leader of a project, provides you performance indexes of his project. The schedule variance (SV) of his project is 25. What does this figure depict?

    A. Project is behind the schedule.

    B. Costs are higher than planned.

    C. Project is right on target.

    D. Project is ahead of the schedule.

  • Question 39:

    Andy is the project manager of the NHGQ project for his organization. He has elected to use a three- point estimate for his project. His project team, however, is complaining about participating in this estimate type because of the time it takes

    to predict the duration of activities. Andy, as the project manager, tells the project team that they must create the time estimate, as it will help this project and future similar projects.

    What is a three-point estimate?

    A. Each activity must be estimated for its optimistic, pessimistic, and most likely duration.

    B. Each activity must be estimated for its optimistic, pessimistic, and most likely duration and then an average for the estimate is created.

    C. A three-point estimate, also known as PERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.

    D. A three-point estimate, also known as GERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.

  • Question 40:

    You are the project manager of the HGH Project. Thomas, your project sponsor, asked you to submit status reports every week, but now he wants you to submit the status reports every other week. What project management plan would you need to update to reflect this change from Thomas?

    A. Scope management plan

    B. Performance management plan

    C. Communications management plan

    D. Project management plan

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.