  • Question 861:

    A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

    A. Verified deliverables

    B. Validated deliverables

    C. Accepted deliverables

    D. Completed change requests

  • Question 862:

    Deciding the phases of project life cycle would be considered a part of which of these knowledge areas?

    A. Project Schedule Management

    B. Project Scope Management

    C. Project Resource Management

    D. Project Integration Management

  • Question 863:

    Which is the tool or technique that is used to obtain the list of activities from the work packages?

    A. Data analysis

    B. Leads and lags

    C. Precedence diagramming method

    D. Decomposition

  • Question 864:

    A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified.

    How many communication channels are available?

    A. 8

    B. 18

    C. 36

    D. 40

  • Question 865:

    During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

    A. Change request

    B. Risk response

    C. Risk management plan

    D. Lessons learned

  • Question 866:

    What is the purpose of tailoring in project management?

    A. To select an appropriate team and its competencies for the project

    B. To select appropriate processes, tools and methodology for the project

    C. To ensure agile practices are embedded into project phases

    D. To let management know the project management will be done efficiency

  • Question 867:

    A project manager held a meeting and listed all team members’ ideas for improving the product on a white board. What data gathering technique did the project manager apply?

    A. Focus groups

    B. Interviews

    C. Brainstorming

    D. Delphi technique

  • Question 868:

    A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

    A. Approved change requests

    B. Verified deliverables

    C. Lessons learned

    D. Work performance data

  • Question 869:

    What is the first step in the Stakeholder Management process?

    A. Plan Stakeholder Engagement

    B. Identify Stakeholders

    C. Manage Stakeholder Responsibility

    D. Monitor Stakeholder Activity

  • Question 870:

    Which of the following is an example of an internal factor that influences the outcome of the project?

    A. Legal restrictions

    B. Financial considerations

    C. Commercial database

    D. Geographic distribution of facilities

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.