  • Question 791:

    The project has a current cost performance index of 0.80. Assuming this performance will continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

    A. $800

    B. $1000

    C. $1250

    D. $1800

  • Question 792:

    Who determines which dependencies are mandatory during the Sequence Activities process?

    A. Project manager

    B. External stakeholders

    C. Internal stakeholders

    D. Project team

  • Question 793:

    Risk exists the moment that a project is:

    A. planned.

    B. conceived.

    C. chartered.

    D. executed.

  • Question 794:

    How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

    A. Keep satisfied

    B. Keep informed

    C. Manage closely

    D. Monitor

  • Question 795:

    The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

    A. dictionary.

    B. chart.

    C. report.

    D. register.

  • Question 796:

    Activity cost estimates are quantitative assessments of the probable costs required to:

    A. Create WBS.

    B. complete project work.

    C. calculate costs.

    D. Develop Project Management Plan.

  • Question 797:

    Who is responsible for initiating a project?

    A. Project sponsor

    B. Project manager

    C. Program manager

    D. Project management office (PMO)

  • Question 798:

    Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

    A. Affinity

    B. Scatter

    C. Fishbone

    D. Matrix

  • Question 799:

    The diagram below is an example of a:

    A. Risk breakdown structure (RBS).

    B. Project team.

    C. SWOT Analysis.

    D. Work breakdown structure (WBS).

  • Question 800:

    Which of the following is an input to the Develop Project Charter process?

    A. Work performance information

    B. Project management plan

    C. Business case

    D. Change requests

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.