Using the following data, what is the Schedule Performance Index (SPI)? EV= $500 PV= $750 AC= $1000 BAC= $1200
A. 0.67
B. 1.5
C. 0.75
D. 0.5
The traditional organization chart structure that can be used to show positions and relationships in a graphic top-down format is called a:
A. Responsible, accountable, consult, and inform (RACI) chart.
B. Matrix-based chart.
C. Human resource chart.
D. Hierarchical-type chart.
The three types of estimates that PERT uses to define an approximate range for an activity's cost are:
A. Parametric, most likely, and analogous.
B. Least likely, analogous, and realistic.
C. Parametric, optimistic, and pessimistic.
D. Most likely, optimistic, and pessimistic.
The run chart created during the Perform Quality Control process on a project is used to show the:
A. relationship between two variables
B. data points plotted in the order in which they occur
C. most common cause of problems in a process
D. frequency of occurrence
The project manager has requested all expert team members to complete an anonymous questionnaire to identify possible risks. This is an example of a technique known as the:
A. interview technique
B. information gathering technique
C. Delphi technique
D. feedback technique
The project governance approach should be described in the:
A. change control plan
B. project scope
C. statement of work
D. project management plan
The project charter is an input to which process?
A. Develop Project Charter
B. Develop Project Management Plan
C. Monitor and Control Project Work
D. Perform Integrated Change Control
The process of developing a detailed description of the project and product is known as:
A. Create WBS.
B. Verify Scope.
C. Collect Requirements.
D. Define Scope.
The Process Group in which the internal and external stakeholders interact and influence the overall outcome of the project is the:
A. Monitoring and Controlling Process Group.
B. Initiating Process Group.
C. Planning Process Group.
D. Executing Process Group.
The Process Group that involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project management plan is known as:
A. Initiating.
B. Planning.
C. Executing.
D. Monitoring and Controlling.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.