A project manager should communicate to stakeholders about resolved project issues by updating the:
A. project records
B. project reports
C. stakeholder notifications
D. stakeholder register
Which project document is updated in the Control Stakeholder Engagement process?
A. Project reports
B. Issue log
C. Lessons learned documentation
D. Work performance information
Which items are components of a project management plan?
A. Change management plan, process improvement plan, and scope management plan
B. Agreements, procurement management plan, and work performance information
C. Schedule management plan, project schedule, and resource calendars
D. Scope baseline, project statement of work, and requirements traceability matrix
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
A. Forecasting,
B. Brainstorming.
C. Historical databases.
D. Cost of quality.
The initial development of a Project Scope Management plan uses which technique?
A. Alternatives identification
B. Scope decomposition
C. Expert judgment
D. Product analysis
Which statement is true about the project management body of knowledge?
A. Recognized by every project manager
B. Constantly evolving
C. The sum of all knowledge related to project management
D. A sum of knowledge that should be applied on every project
What are the identified risks for doing excessive decomposition in a WBS?
A. Insufficient project funding and disqualification of sellers
B. Insufficient project funding and ineffective use of resources
C. Disqualification of sellers and non-productive management efforts
D. Non-productive management effort and inefficient use of resources
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
A. Control Scope
B. Collect Requirements
C. Create WBS
D. Define Scope
Which of the following is a strategy to deal with positive risks or opportunities?
A. Mitigate
B. Transfer
C. Exploit
D. Avoid
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
A. The risk of achieving the shortened project time is increased.
B. The critical path will have positive total float.
C. Contingency reserves are released for redeployment by the project manager.
D. Duration buffers are added to maintain a focus on planned activity durations.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.