  • Question 161:

    Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

    A. Work performance data

    B. Project documents

    C. Scope baseline

    D. Requirements documentation

  • Question 162:

    Which input to the Plan Risk Management process provides information on high-level risks?

    A. Project charter

    B. Enterprise environmental factors

    C. Stakeholder register

    D. Organizational process assets

  • Question 163:

    The Perform Integrated Change Control process occurs in which Process Group?

    A. Initiating

    B. Executing

    C. Monitoring and Controlling

    D. Planning

  • Question 164:

    An output of the Validate Scope process is:

    A. A requirements traceability matrix.

    B. The scope management plan.

    C. Work performance reports.

    D. Change requests.

  • Question 165:

    Plan Schedule Management is a process in which Knowledge Area?

    A. Project Scope Management

    B. Project Human Resource Management

    C. Project Integration Management

    D. Project Time Management

  • Question 166:

    Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

    A. Project team

    B. Focus group

    C. Change control board

    D. Project stakeholders

  • Question 167:

    Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

    A. Estimate Costs

    B. Control Costs

    C. Determine Budget

    D. Plan Cost Management

  • Question 168:

    Which document describes the necessary information to determine if a project is worth the required investment?

    A. Cost baseline

    B. Service level agreement

    C. Memorandum of understanding

    D. Business case

  • Question 169:

    An element of the project scope statement is:

    A. Acceptance criteria.

    B. A stakeholder list.

    C. A summary budget.

    D. High-level risks.

  • Question 170:

    Which tool or technique is effective in a project in which the deliverable is not a service or result?

    A. Inspection

    B. Variance analysis

    C. Decomposition

    D. Product analysis

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.