A regression line is used to estimate:
A. Whether or not a process is stable or has predictable performance.
B. How a change to the independent variable influences the value of the dependent variable.
C. The upper and lower specification limits on a control chart.
D. The central tendency, dispersion, and shape of a statistical distribution.
Reserve analysis is a tool and technique used in which process?
A. Plan Risk Management
B. Plan Risk Responses
C. Identify Risks
D. Control Risks
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
A. Close Project or Phase
B. Conduct Procurements
C. Control Procurements
D. Close Procurements
An input to the Plan Procurement Management process is:
A. Source selection criteria.
B. Market research.
C. A stakeholder register.
D. A records management system.
Which process numerically analyzes the effect of identified risks on overall project objectives?
A. Plan Risk Management
B. Plan Risk Responses
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis
An output of the Manage Stakeholder Engagement process is:
A. change requests
B. enterprise environmental factors
C. the stakeholder management plan
D. the change log
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
A. Responses
B. Appetite
C. Tolerance
D. Attitude
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:
A. Human resource management plan.
B. Activity resource requirements.
C. Personnel assessment tools,
D. Multi-criteria decision analysis.
The process of identifying and documenting relationships among the project activities is known as:
A. Control Schedule.
B. Sequence Activities.
C. Define Activities.
D. Develop Schedule.
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
A. Enterprise environmental factors
B. Work performance reports
C. Organizational process assets
D. Context diagrams
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.