  • Question 841:

    Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

    A. Stakeholder register

    B. Scope management plan

    C. Stakeholder management plan

    D. Project charter

  • Question 842:

    Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

    A. Project Risk Management

    B. Project Human Resource Management

    C. Project Scope Management

    D. Project Stakeholder Management

  • Question 843:

    A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

    A. Identify Risks

    B. Control Risks

    C. Perform Quantitative Risk Analysis

    D. Perform Qualitative Risk Analysis

  • Question 844:

    Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

    A. Direct and Manage Project Work

    B. Develop Project Management Plan

    C. Plan Quality Management

    D. Monitor and Control Project Work

  • Question 845:

    Inputs to the Plan Schedule Management process include:

    A. Organizational process assets and the project charter,

    B. Enterprise environmental factors and schedule tools.

    C. Time tables and Pareto diagrams.

    D. Activity attributes and resource calendars.

  • Question 846:

    Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

    A. Direct

    B. Interactive

    C. Pull

    D. Push

  • Question 847:

    Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

    A. Cost variance (CV)

    B. Cost performance index (CPI)

    C. Budget at completion (BAC)

    D. Variance at completion (VAC)

  • Question 848:

    Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

    A. Bottom-up

    B. Parametric

    C. Analogous

    D. Three-point

  • Question 849:

    Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

    A. Nominal group technique

    B. Idea/mind mapping

    C. Affinity diagram

    D. Brainstorming

  • Question 850:

    When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

    A. Negative

    B. Zero

    C. Positive

    D. Free

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.