  • Question 61:

    Budgets reserved for unplanned changes to project scope and cost are:

    A. Contingency reserves.

    B. Management reserves.

    C. Authorized budgets.

    D. Cost baselines.

  • Question 62:

    In which of the following types of organizations is resource availability moderate to high?

    A. Weak matrix

    B. Balanced matrix

    C. Strong matrix

    D. Projectized

  • Question 63:

    The process of developing a detailed description of the project and product is known as:

    A. Create WBS.

    B. Verify Scope.

    C. Collect Requirements.

    D. Define Scope.

  • Question 64:

    Which of the following is a tool or technique for the Plan Procurements process?

    A. Bidder conferences

    B. Proposal evaluation techniques

    C. Contract types

    D. Contract change control systems

  • Question 65:

    Which of the following will provide the basis for estimating, scheduling, executing, and monitoring and controlling project work?

    A. Activities

    B. Milestone list

    C. Work breakdown structure (WBS)

    D. Work packages

  • Question 66:

    Which of the following tools will be used to produce performance reports that provide information to stakeholders about project cost, schedule progress, and performance?

    A. Communications methods

    B. Reporting systems

    C. Forecasting methods

    D. Variance analysis

  • Question 67:

    Which process group contains the processes performed to finalize all activities?

    A. Planning Process Group

    B. Executing Process Group

    C. Monitoring and Controlling Process Group

    D. Closing Process Group

  • Question 68:

    Which of the Project Time Management processes analyzes activity sequencing, durations, resource requirements, and schedule constraints?

    A. Estimate Activity Durations

    B. ControlSchedule

    C. Sequence Activities

    D. Develop Schedule

  • Question 69:

    Which of the following is used to illustrate the connections between work packages or activities and project team members?

    A. Hierarchical-type charts (HTC)

    B. Organizational breakdown structure (OBS)

    C. Work breakdown structure (WBS)

    D. Responsibility assignment matrix (RAM)

  • Question 70:

    Which of the following methods of performance review examines project performance over time to determine if performance is improving or deteriorating?

    A. Earned value performance

    B. Trend analysis

    C. Cost-benefit analysis

    D. Variance analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.