  • Question 51:

    The Administer Procurements process is in which of the following Project Management Process Groups?

    A. Planning

    B. Monitoring and Controlling

    C. Initiating

    D. Executing

  • Question 52:

    Which document describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results?

    A. Procurement management plan

    B. Procurement statement of work

    C. Request for proposal

    D. Request for quote

  • Question 53:

    A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?

    A. What-if scenario analysis

    B. Critical chain method

    C. Schedule crashing

    D. Resource leveling

  • Question 54:

    Projects are authorized by which of the following individuals?

    A. Project managers

    B. Stakeholders

    C. Functional managers

    D. Sponsors

  • Question 55:

    Outputs from constituent processes might be used as:

    A. Inputs to other processes.

    B. Proof of process completion.

    C. Identification of project tasks.

    D. Indicators to eliminate project redundancies.

  • Question 56:

    Design of experiments (DOE) should be used during which of the following processes?

    A. Perform Quality Assurance

    B. Total Quality Management

    C. Perform Quality Control

    D. Plan Quality

  • Question 57:

    Overlooking negative stakeholders can result in a/an:

    A. decreased likelihood of conflicting interests between stakeholders.

    B. decreased likelihood of the projects progress being impeded.

    C. increased likelihood of project failure.

    D. increased likelihood of project success.

  • Question 58:

    Which type of team can be defined as a group of people with a shared goal who fulfill their roles although spending little or no time meeting face to face?

    A. Co-location team

    B. Virtual team

    C. Departmental team

    D. Consultant team

  • Question 59:

    Which of the following are documented directions to perform an activity that can reduce the probability of negative consequences associated with project risks?

    A. Recommended corrective actions

    B. Recommended preventive actions

    C. Risk audits

    D. Risk reassessments

  • Question 60:

    Which of the following makes changes to formally control documentation to reflect modified or additional ideas or content?

    A. Defect repair

    B. Updates

    C. Corrective action

    D. Performance reports

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.